A useful global benchmark is about $10,700 per kW for data-center shell-and-core construction in 2025. JLL forecasts about $11,300 per kW for 2026. Neither figure is an all-in price for usable IT capacity: the estimates exclude land and active IT equipment, and tenant technology fit-out is separate.
What the per-kW benchmark includes
JLL Research’s 2026 Global Data Center Outlook reports a 2025 global average of $10.7 million per MW and forecasts $11.3 million per MW for 2026. Since 1 MW equals 1,000 kW, dividing each figure by 1,000 gives $10,700 and $11,300 per kW, respectively.
As an Amazon Associate I earn from qualifying purchases.
These are construction benchmarks, not project quotes. JLL says its figures include the cost to construct the shell and core and exclude land acquisition and active IT equipment. Its city comparisons use a single-tenant, 50 MW, air-cooled data-center baseline. The reported denominator is data-center capacity; it should not be treated as a more precisely defined measure of planned IT load than the source provides.
Construction and project investment are different totals
Before using a per-kW figure in a budget, define what is in the numerator. A full project estimate may need to account separately for land, shell and core, mechanical and electrical systems, tenant fit-out, active IT equipment, contingency and financing. The JLL global benchmark is not an estimate of all those costs combined.
#1 Best Overall
- 8 POWERFUL NEMA C13 OUTLETS: Rack mount PDU provides up to 16A/120V (1920VA) or 20A/240V (4800 VA) for servers & equipment; 1U rack space for easy accessibility; 10ft/3m C19 to NEMA5-20p cord incl.
- 3600 JOULE CIRCUT PROTECTION: Built-in resettable circuit breaker that acts as a surge protector or shields from unintentional overloads in data center; Safety listed for performance and peace of mind
- CONFIGURABLE EIA-310D COMPLIANT DESIGN: Installable in standard 19in. 2 or 4 post rack using incl. cage nuts/screws; C20 power cord allows any local plug config for 120 or 240 V single phase in/out
- SPECS: 1U 19in. Horizontal PDU | 8x IEC C13 Pwr out | C20 Pwr input (1 phase) | Load cap. @ 120V/16A (1920VA) |Load cap. @240V/20A (4800VA) | 3600 J surge sup. w/breaker |EIA-310D |Mounting H.W. incl.
For AI infrastructure, JLL says tenant technology fit-out can cost as much as $25 million per MW, equivalent to up to $25,000 per kW. That is an upper-end figure, not a typical add-on for every data center, and it is separate from the shell-and-core construction benchmark.
How location and design affect construction cost
JLL’s 2026 market examples, converted from dollars per MW to dollars per kW, show substantial variation:
Rank #2
- Versatile and Space-Saving: This 1U Rack mount PDU features a compact design that allows for efficient use of space in standard 19-inch racks. 16 rear-facing plug outlets and three front-facing outlets provide ample connectivity for your devices
- Efficient USB Power: Featuring four USB ports, it enables simultaneous power supply to your favorite devices, ensuring convenience and productivity
- Built-in Circuit Breaker: The PDU is equipped with a built-in 12-Amp circuit breaker that protects against circuit overloads. This ensures reliable performance and helps prevent damage to your equipment
- Heavy-Duty Construction: The power distribution unit is designed with heavy-duty components and a sturdy metal housing for durability and long-lasting use
- Convenient Mounting: The PDU features mounting ears on the back panel for easy installation in a standard 19-inch rack
| Market | Shell-and-core estimate per kW | Basis |
|---|---|---|
| Tokyo | $14,000–$18,000 | JLL 2026 market example; 50 MW, single-tenant, air-cooled baseline |
| Chicago | $12,000–$14,000 | JLL 2026 market example; 50 MW, single-tenant, air-cooled baseline |
| London | $12,000–$14,000 | JLL 2026 market example; 50 MW, single-tenant, air-cooled baseline |
| Mumbai | $6,000–$7,000 | JLL 2026 market example; 50 MW, single-tenant, air-cooled baseline |
These are city-specific estimates, not prices that can be applied to an entire country or region. JLL also states that liquid-cooled facilities carry a 10% cost premium and that multistory facilities in the Americas add 20% to construction costs. Treat those adjustments as JLL’s assumptions, not universal rules for every design or market.
PC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11Outdated Drivers Are Slowing You Down
One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware matchWhy published cost indexes may not match
Benchmarks can cover different work, so a larger or smaller per-kW number does not necessarily mean a project is more or less expensive on a like-for-like basis. Turner & Townsend’s 2025 methodology groups shell and core, architectural fit-out and finishes, mechanical and electrical fit-out, contractor preliminaries, contractor margin, contractor contingency, and mechanical and electrical equipment.
Rank #3
- Reliable Power Distribution - Backed by a 3 year warranty, this power strip surge protector can deliver 120, 125, or 240V AC at 15 or 30A, optimized for networking, telecom, crypto mining, or security.
- Designed For Your Safety - This rack mount PDU has a built-in surge protector to help minimize overloads. It also has volt and amp meters in it with a clear display for convenient monitoring of loads.
- Power Up Your Server - This PDU power strip can fit in 1U of EIA-standard 19” server racks with two or four posts. It’s switchless to avoid accidental shutdowns that can lead to costly downtimes.
- Connect Multiple Loads - Our rack mount power strips have 6 or 8 C13 rear outlets, a NEMA L6-30P input plug, and a 6’ or 10’ heavy-duty cable for connecting to a utility outlet, generator, or UPS.
- Easy Installation - This power strip has a reversible 19" metal case so it can face either the front or rear of your rack. Ears and fittings are included in the rack mount for faster PDU installation.
That methodology draws on more than 300 live or recent projects in more than 20 countries, converts costs to US dollars using the average exchange rate from 1 October 2024 to 1 October 2025, and supplements the data with a poll of more than 280 industry experts. Because this scope differs from JLL’s shell-and-core-only benchmark, compare their figures only after reconciling included work, currency basis, location and facility assumptions. Turner & Townsend’s reported 9% global average year-on-year increase in its 2024 index is historical context, not a forecast or a 2026 escalation rate (2024 index coverage).
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Do not confuse construction cost with colocation rent
Colocation is a recurring service charge, not the capital cost of constructing a facility. CBRE reported an average asking price of $174.06 per kW per month in H1 2024 across primary North American wholesale colocation markets for a 250–500 kW requirement. That dated, market-specific asking price (CBRE Research) cannot be substituted for a one-time construction cost per kW.
Quick Recap
Best Value
- 【Heavy-Duty 9 Outlet PDU】 Designed for standard 19" server racks, this 1U rack mount power strip provides 9 US standard outlets (15A/125V/1875W), ideal for data centers, network cabinets, and audio-visual setups needing reliable power distribution.
- 【Individual Switch Control】 Each outlet is equipped with its own illuminated on/off switch, so you can manage connected devices individually instead of unplugging them. The switch modules are fully independent: if one outlet trips, only that outlet shuts down while all remaining outlets keep running normally — no whole-strip shutdown, no interruption to your other equipment. A tripped switch also tells you exactly which device has reached its load limit, giving you faster, more sensitive overload protection and a clear visual cue for troubleshooting.
- 【Overload Protection & Power Monitoring】 Equipped with overload protection and a digital power monitoring display, this PDU safeguards your equipment from overloads while providing real-time voltage and current data for secure operation. The switch will automatically trip if the current exceeds 15A. Simply having wires or cables touch the switch will not cause it to trip — the switch only responds to an overload condition.
- 【Durable Metal Construction】 Built with a sturdy metal housing and a 14AWG heavy-duty 6.5FT power cord, ensuring durability and stable performance even in high-demand environments like professional server rooms and industrial settings.
- 【Versatile Installation】 Ideal for studios, labs, and data centers, ensuring peak performance and reliability. Designed for 1U rackmount for hassle-free cable management. Supports horizontal installation in server racks with included mounting brackets.
Rank #4
- 100-125V/15A Basic Power Distribution Unit (PDU) delivers AC power to data centers, network closets, and other electrically demanding applications
- OUTPUT: 10 Rear NEMA 5-15R Outlets; INPUT: NEMA 5-15P straight plug with 15 ft power cord
- VERSATILE RACKMOUNT OPTIONS: Allows for the PDU to be installed vertically or horizontally
- ADDITIONAL FEATURES: Network-grade plugs and outlets, durable metal housing, and cord retention tray
- 3-YEAR LIMITED WARRANTY (This unit does not provide surge suppression)
How to use the figure in a budget
- Choose the cost boundary. Decide whether the estimate is shell and core only or also includes mechanical and electrical fit-out, land, tenant fit-out, IT equipment, contingency and financing.
- Match the capacity basis. State whether the denominator is planned IT load or another capacity measure; do not imply the JLL benchmark specifies a more exact denominator than it does.
- Use a relevant location and design. A global average is an anchor, not a local quote. Compare the same city or market, facility size, cooling approach and building configuration.
- Label the year and status. Keep the 2025 reported average distinct from JLL’s 2026 forecast, and do not blend either with historical construction indexes or monthly colocation charges.
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.
Quick wins for a faster PC:
Fix the driver behind crashes, sound loss and screen glitchesFind Drivers →Repair Windows errors before they cause bigger problemsFix Now →Scan for outdated or missing drivers - takes under a minuteDriver Scan →