T5 Data Centers acquired a seven-acre, data-center-zoned site in Elk Grove Village, Illinois, and announced plans to build a 220,000-square-foot facility there with 36 MW of critical IT capacity. The project, called CHI V, was targeted for occupancy in 2028. It is a land acquisition and development plan—not an operating data center. Its significance is the effort to secure a powered, entitled site in Chicago’s O’Hare data-center corridor years ahead of delivery.
What T5 acquired—and what it plans to build
T5 announced the acquisition on March 26, 2025. Its announcement describes CHI V as a seven-acre Elk Grove Village site already zoned for data-center use. The company said it planned a 220,000-square-foot facility designed for high-density cloud computing and artificial-intelligence workloads, with 36 MW of critical IT capacity and occupancy targeted for 2028. T5’s announcement and Data Center Dynamics’ coverage describe the plan; neither makes the target date a guarantee.
A commercial-real-estate source identifies the property as 950 and 1050 Morse Avenue and reports a transaction value above $21.3 million. T5 did not disclose a purchase price in its announcement, so that figure should be treated as third-party reporting, not an officially confirmed price. Van Vlissingen & Co.’s report
Dividing the announced 36 MW of critical IT capacity by 220,000 square feet gives roughly 164 watts per square foot. That is only a rough comparison of the two announced figures—not total building-power density or a specification for individual racks. The public announcement does not establish the number of GPU racks, tenants, cooling design, power-usage effectiveness (PUE), or annual energy consumption.
Outdated Drivers Are Slowing You Down
One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware matchWindows Errors? Fix Them Before They Spread
Repair common Windows errors and clear accumulated junk for a smoother, more stable PC - no reinstall needed.Free scan · no reinstall#1 Best Overall
- Save valuable floor space: 6U wall mount server cabinet Dimensions: 13.78" H x21.65" W x17.72" D.Maximum mounting depth is 14.2"
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access. Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punch-out panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
Why the site’s power path matters
T5 said it had completed the steps needed to secure utility power from ComEd and planned to begin construction shortly after the announcement. That is a statement about the project’s utility arrangements, not confirmation that the facility had been energized or that all required electrical infrastructure was complete. A data center’s critical IT capacity is not interchangeable with its total utility load: cooling, power conversion, backup systems, and other building needs also require infrastructure.
Power availability can determine whether a development site is usable on the schedule customers need. A filing with the Illinois Commerce Commission documents substantial ComEd work associated with new data-center customers in Elk Grove, including electric-service infrastructure and transmission lines. It illustrates the scale of utility investment involved in serving the area, but does not establish that each listed item was for CHI V. Illinois Commerce Commission filing
For a developer, a site with suitable zoning and a credible utility path can be more useful than a larger parcel without either. Connectivity, permitting, construction, equipment procurement, commissioning, and utility delivery still have to align before a planned facility can serve customers.
Why Elk Grove Village and the O’Hare corridor attract projects
Elk Grove Village is an established data-center location near O’Hare International Airport, with industrial infrastructure and access to a substantial carrier and network ecosystem. The village has promoted itself as a technology and data-center hub. In a 2020 municipal release, it described the community as having the Midwest’s highest concentration of data centers at that time, citing 12 facilities and more than 2.6 million square feet. That is a historical municipal claim, not a current market count. Elk Grove Village’s release
Free tools Windows power users keep installed
One-click scans. No signup required.
Chicago’s broader appeal also includes its central U.S. location and an established base of carriers, cloud providers, enterprises, and data-center operators. Illinois’ 2024 data-center report provides state-level investment and policy context, but eligibility and the terms of any incentive depend on the specific program and project; the report alone does not establish that CHI V receives a particular benefit. Illinois Department of Commerce and Economic Opportunity, 2024 report
How CHI V fits T5’s Chicago portfolio
T5 described CHI V as its fifth data-center location in the Chicago market and its fourth project in the O’Hare submarket in recent years. Those are the company’s portfolio labels; they do not mean that five T5 Chicago facilities were operating when the acquisition was announced. CHI V was a development site for a proposed facility.
Rank #2
- Save valuable floor space: 12U wall mount server cabinet Dimensions: 24.25" H x21.65" W x17.72" D. MAXIMUM MOUNTING DEPTH is 14.2".
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access; Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punchout panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
The announcement referenced T5’s Chicago I and Chicago II locations in Elk Grove Village, Chicago III in Northlake, and Chicago IV in Grayslake, alongside the new CHI V site. Chicago III is a separate project: Data Center Dynamics later reported that it topped out at about 250,000 square feet and 36 MW. Those specifications and that construction milestone should not be attributed to CHI V. Data Center Dynamics on Chicago III
What the 36 MW plan says about AI—and what it does not
T5 explicitly positioned CHI V for high-density cloud and AI applications. That makes the proposed capacity relevant to buyers seeking large blocks of computing infrastructure, but 36 MW by itself does not reveal how many servers or accelerators the facility could host. The answer would depend on deployment design, rack density, cooling, redundancy, and how much of the site’s power is available to IT equipment.
Do these 3 things before closing this tab:
1Clear out junk files and repair common Windows errors2Fix the driver behind crashes, sound loss and screen glitches3Repair Windows errors before they cause bigger problemsAI workloads can put greater demands on power distribution and heat removal than conventional deployments. Yet T5’s public announcement does not specify whether CHI V will use liquid cooling, a closed-loop system, or another cooling architecture, nor does it state water use or PUE. Those details cannot be inferred from a separate developer’s project.
Competition signals demand, not a guaranteed shortage measure
T5’s acquisition came amid other development activity in Elk Grove Village. STACK Infrastructure separately announced a 263,000-square-foot facility with 36 MW of capacity for AI and cloud workloads. That project is not part of CHI V, and its design details should not be applied to T5’s site. The two announcements show multiple developers pursuing capacity in the same submarket; they do not, on their own, quantify vacancy or prove that all planned capacity will be leased. STACK’s announcement
T5 said available data-center space in the O’Hare market was limited. Separately, Data Center Knowledge’s March 28, 2025 report cited an Omdia estimate of more than 70 data centers in Chicago and described vacancy as historically low. These claims depend on the source’s market definition, date, and methodology; they are not a universal, continuously updated measure of availability. Data Center Knowledge’s report
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Risks between site acquisition and customer-ready capacity
Utility delivery and schedule
Securing a utility arrangement does not eliminate the risk of delays in interconnection, substations, transmission work, or other infrastructure. A 2028 occupancy target leaves multiple delivery steps to complete, and no source cited here verifies CHI V’s energization or a revised construction schedule.
Rank #3
- Sturdy:4u server rack is construct from cold rolled steel, with a weight capacity of 110lbs(50kg); Electrostatic powder coat prevents rust and corrosion,quality finish
- Direct use:Open and use, not having to assemble it.Network rack can be placed flat or mounted on the wall,also can be installed vertically under the table
- Design Features:maximum mounting depth of 14 in,cables can be fixed on the side panel;Open frame server rack achieves effortless inspection, replacement and assemble
- Installation:wall mount network rack is easy to install,with instructions or videos for reference;Equipped with multiple accessories, suitable for different needs
- Application:EIA/ECA-310-E Compliant;wall mounted 4u rack fits all 19" racks and cabinets to hold various IT, network, and AV equipment;wall mount rack available in 4U, 6U, and 8U to choose
Permits, construction, and procurement
Data-center zoning is an important starting point, not a substitute for project approvals, building permits, construction, equipment delivery, and commissioning. The cited public material does not identify CHI V’s general contractor, equipment suppliers, tenant commitments, or a commissioning schedule.
Cooling, water, and community effects
High-density computing requires effective heat removal. Without a disclosed design, CHI V’s cooling method and water impact are unknown. Noise, backup generation, land use, and utility infrastructure can also shape local review and community acceptance.
Demand and financing
Long lead times require developers to commit capital before all future customer demand is certain. Cloud buyers may change deployment timing, improve server utilization, or choose other regions. Interest rates, equipment lead times, and tenant concentration can also affect project economics. The cited sources do not establish that CHI V is financed, fully leased, or pre-sold.
What buyers and local stakeholders should watch
For a prospective customer, a headline capacity figure is only a starting point. The practical questions are when usable power will be available, what density and cooling the facility can support, how resilient its utility and network connections are, and what lease structure and delivery commitments apply. Local stakeholders may also want to follow permitting, utility work, and disclosures about water, noise, and backup generation.
The Tool Desk
Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →- Building permits, site work, and any announced construction milestones.
- ComEd infrastructure and delivery milestones, without assuming that area-wide utility work is specific to CHI V.
- Tenant or build-to-suit announcements and the project’s intended service model.
- Cooling-system, water-use, and power-efficiency disclosures.
- Any revised delivery date or local economic-development and incentive approvals.
As of August 16, 2026, the sources cited here establish the acquisition announcement, proposed specifications, and original 2028 target; they do not independently establish that CHI V opened, secured tenants, received delivered power, or reached a later construction milestone.