Halloween DealsAmazon USHalloween week deals: useful picks before month-endAmazon US: current deals, useful picks and tech finds.Check DealsSlow PC?RecommendedPC slow today? Run a repair scan before it gets worseResolve common Windows issues and optimize system performance.Scan NowHalloween DealsAmazon USOctober picks are moving - compare before checkoutAmazon US: current deals, useful picks and tech finds.See Picks×
Skip to content
The Finance Base
The Money Desk · Blog
Re:

OpenAI’s Five New Stargate Data Centers: Locations, Costs and What Has Changed

OpenAI announced five new Stargate sites with Oracle and SoftBank in September 2025. Here are the locations, planned capacity, financing, construction status and key risks.
From TheFinanceBase Team8 min to read
Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

OpenAI, Oracle and SoftBank announced five new U.S. Stargate sites on September 23, 2025—but they were announced projects, not five completed data centers. The locations were identified as Shackelford County, Texas; Doña Ana County, New Mexico; Wisconsin; Lordstown, Ohio; and Milam County, Texas. OpenAI said the broader Stargate portfolio represented nearly 7 gigawatts of planned capacity and more than $400 billion in investment over three years at that point.

For households, investors and workers, the important distinction is between planned capacity, construction, energized facilities and operating AI workloads. The five-site announcement has since become part of a larger U.S. infrastructure program that includes a Michigan campus and later capacity claims.

As an Amazon Associate I earn from qualifying purchases.

The five sites at a glance

Site State Primary partners What was announced How to read the status
Shackelford County Texas Oracle and OpenAI Part of the Oracle-related expansion Announced project; the September release did not establish that it was operational.
Doña Ana County New Mexico Oracle and OpenAI Part of the Oracle-related expansion Announced project; capacity was included in broader planned figures.
Wisconsin Wisconsin Oracle, OpenAI and Vantage Data Centers The unnamed Midwest site from the original announcement Identified later; Oracle and Vantage were named in the subsequent clarification.
Lordstown Ohio SoftBank and OpenAI Designed to scale as part of the SoftBank-related buildout OpenAI described it as on track to become operational in 2026, but that does not by itself prove operation or full capacity.
Milam County Texas SoftBank, OpenAI and SB Energy A site designed to scale to 1.2 gigawatts In January 2026, SB Energy was selected to build and operate the facility.

The locations and partner split come from OpenAI’s September 2025 announcement. The Midwest site was later identified as Wisconsin, with Oracle partnering with Vantage Data Centers.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

What OpenAI actually announced

The September announcement covered five new sites: three associated with Oracle and two associated with SoftBank. OpenAI said the projects, the flagship Abilene, Texas campus and ongoing CoreWeave projects together represented nearly 7 GW of planned capacity and more than $400 billion in investment over three years.

#1 Best Overall
Tecmojo 6U Wall Mount Server Cabinet IT Network Rack Enclosure Lockable Door and Side Panels Black, Cooling Fan, Standard Glass Door, 450mm Depth, for 19” IT Equipment, A/V Devices
  • Save valuable floor space: 6U wall mount server cabinet Dimensions: 13.78" H x21.65" W x17.72" D.Maximum mounting depth is 14.2"
  • Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access. Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
  • Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punch-out panels for easy cable access
  • Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
  • PCI & HIPPA and EIA/ECA-310-E compliant

Those figures describe a portfolio of announced and developing infrastructure. They are not proof that $400 billion had already been spent, that every site had been financed in full, or that nearly 7 GW was already supplying AI workloads.

The announcement also mentioned a potential 600-megawatt expansion near Abilene. That expansion was separate from the five new sites and should not be counted as a sixth new data center—or folded into the five-site count without explanation.

Oracle and SoftBank are not building identical three-company projects

The headline can make Stargate sound like one uniform construction venture in which OpenAI, Oracle and SoftBank jointly build each facility. The actual structure is more complicated.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Oracle-related projects

Oracle was associated with the Shackelford County, Doña Ana County and Wisconsin projects. Oracle separately announced an agreement with OpenAI in July 2025 to develop up to 4.5 GW of additional Stargate capacity. OpenAI said that broader Oracle agreement exceeded $300 billion between the companies over five years and estimated more than 100,000 jobs across construction, operations, manufacturing and local services. That larger estimate should not be treated as a job count for only the five September sites.

OpenAI also said more than 2 million chips were expected to run across the additional Oracle-related capacity under development. This was a planned deployment estimate, not a count of chips already installed.

SoftBank-related projects

Lordstown and Milam County were the two SoftBank-related sites. Milam County was to be developed with SB Energy, a SoftBank Group company. In January 2026, OpenAI and SoftBank each invested $500 million in SB Energy, and OpenAI selected SB Energy to build and operate the previously announced 1.2-GW Milam County site.

Rank #2
AxcessAbles 12U Network Rack with Wheels - 500lb Capacity, 18" Depth | 19-Inch Open Frame AV Rack Case with 3” Caster Wheels | Screws, Spacer, Tool Included
  • Universal 19” Rack Mount Compatibility – Perfect for pro audio, video, IT, and network gear. Compatible with mixers, routers, patch panels, servers, power amps, and more.
  • Heavy-Duty Load Capacity – Built to support up to 550 lbs. Ideal for studio gear, DJ setups, server equipment, and AV components that demand serious stability.
  • Robust Steel Frame & Design – Made with 1.5mm thick steel and weighs 36 lbs for maximum durability, reduced vibration, and long-term reliability in any setting.
  • Mobile & Secure – Preinstalled with 3” industrial-grade caster wheels (lockable), making it easy to move and position your rack exactly where you need it.
  • All-In-One Setup Kit Included – Comes with 34 rack screws (5mm & 6mm), a 1U blank spacer, and an assembly tool—ready for fast installation out of the box.

According to the companies, the Milam County design aims to minimize water use and includes new generation intended to protect Texas ratepayers. That is a project-specific commitment—not evidence that every Stargate campus will have the same water or energy profile.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

What Stargate is

Stargate is an infrastructure platform, not the name of one building. It encompasses data-center development, cloud services, AI chips, energy, financing, construction and operations.

The original January 2025 Stargate announcement described an intended $500 billion investment over four years, with $100 billion to be deployed immediately. It named SoftBank, OpenAI, Oracle and MGX as initial equity funders. SoftBank was assigned financial responsibility, while OpenAI was assigned operational responsibility.

The broader technology and infrastructure network includes Arm, Microsoft, NVIDIA, Oracle, CoreWeave, Vantage Data Centers, SB Energy and construction and real-estate partners. Their roles vary by project. Microsoft, for example, was expected to continue providing cloud services to OpenAI even as Stargate added physical infrastructure.

What the capacity numbers mean

A gigawatt is a measure of power, not a count of buildings. In data-center announcements, “GW” can refer to different stages or concepts:

What’s actually slowing this PC down?

Pick the symptom - the matching free tool is one click away.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
  • Planned power capacity for a campus or portfolio
  • Potential or scalable future capacity
  • IT load available to computing equipment
  • Capacity under development or contracted
  • Power that has been energized
  • Capacity actually running training or inference workloads

These distinctions matter. A campus may be designed to scale to a stated maximum while only part of that capacity is built, connected to the grid or filled with operating servers. The September 2025 figures combined current, planned, potential and scalable elements, so they should not be presented as operating capacity.

Rank #3
Sale
StarTech 22U 4-Post Server Cabinet, 33in/83cm Deep, 1764lb (RK2236BKF) | 19in enclosed enterprise steel rack, Adjustable depth 5.7in-33in, Lockable vented doors, Casters & feet
  • ADJUSTABLE DEPTH: 4- Post 22U 19" server rack enclosure with 4 vertical rails and adjustable mounting depth 5.7" to 33.0" (14,4cm to 83,8cm); IT rack is compatible with various servers / switches / data / video / AV and other IT networking equipment
  • EASY SHIPPING AND ASSEMBLY: Enclosed 22U data rack cabinet ships compact flat-packed to avoid damage and facilitate installation; Include wheels & levelling feet to offer more stability; Home server rack cabinet is only 46.6in (118,3cm) in height
  • DESIGN AND VENTILATION: Half height server rack cabinet has lockable and removable door and side panels with vented top allowing airflow; 4 Post 19" rack with 1764lb (800kg) weight capacity (stationary); Computer cabinet rack is EIA/ECA-310-E Compliant
  • HARDWARE INCLUDED: Rolling home network rack includes rack mounting and equipment mounting hardware, such as 20 M6 cage nuts / screws, PVC cup washers; Front/rear doors and side panels Keys, 2x allen keys; Rack assembly hardware; Casters and leveling feet
  • THE IT PRO'S CHOICE: Designed and built for IT Professionals, this 22U IT Server Cabinet is backed for life, including free lifetime 24/5 multi-lingual technical assistance

How the project changed after September 2025

  • January 21, 2025: OpenAI, SoftBank, Oracle and MGX announced Stargate, including the intended $500 billion and 10-GW U.S. commitment.
  • July 22, 2025: OpenAI and Oracle announced up to 4.5 GW of additional capacity.
  • September 23, 2025: The five new U.S. sites were announced.
  • October 22, 2025: The previously unnamed Midwest site was identified as Wisconsin.
  • October 30, 2025: OpenAI announced a Stargate campus in Saline Township, Michigan, and said the broader portfolio had reached more than 8 GW of planned capacity and over $450 billion in investment over three years.
  • January 9, 2026: OpenAI and SoftBank announced the SB Energy partnership, including the 1.2-GW Milam County project.
  • April 29, 2026: OpenAI said Stargate had surpassed its initial 10-GW milestone and added more than 3 GW in the preceding 90 days.
  • June 1, 2026: OpenAI said construction had begun on “The Barn,” a 1-GW Stargate campus in Saline Township, Michigan.

That timeline is why a current article should not describe the September announcement as the final Stargate plan. Michigan is an additional campus, and later OpenAI statements describe a portfolio larger than the original five-site announcement.

What was already operating?

OpenAI later said the flagship Abilene campus was operating on Oracle Cloud Infrastructure with NVIDIA GB200 systems, with early training and inference workloads underway. Abilene was the original flagship campus, not one of the five new sites announced in September 2025.

The available announcements do not establish that all five newly announced sites were operational, energized or running at their stated maximum capacity. Lordstown was described as on track for operation in 2026; Milam County received a more detailed build-and-operate arrangement in January 2026; and the Wisconsin, Shackelford County and Doña Ana County announcements identify projects without establishing identical construction milestones.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Who pays, builds and operates the facilities?

There is no single answer for every campus:

  • OpenAI: The principal AI customer, with operational responsibility for Stargate and responsibility for specifying and using the infrastructure.
  • SoftBank: A lead partner assigned financial responsibility in the original announcement and involved in design, energy development and SB Energy.
  • Oracle: A major infrastructure and cloud partner developing substantial capacity and operating the Abilene campus through Oracle Cloud Infrastructure.
  • SB Energy: A SoftBank Group company selected to build and operate the Milam County facility and provide related energy infrastructure.
  • Other partners: NVIDIA supplies accelerators; Microsoft continues its cloud relationship with OpenAI; CoreWeave, Vantage, construction firms, real-estate developers, lenders and energy companies participate in different parts of the broader network.

The $500 billion figure is therefore a long-term infrastructure commitment, not necessarily a single upfront payment from OpenAI, Oracle and SoftBank. Project finance, equity, leases, debt and outside capital can all be part of the structure. For example, the Michigan campus announcement referenced Related Digital equity, Blackstone-affiliated funds and long-term debt financing anchored by PIMCO-managed funds.

Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

Why this matters to households and local economies

Electricity and the grid

AI campuses require far more than buildings and servers. They need generation, transmission, substations, cooling, permits, land and construction labor. OpenAI has identified those requirements as factors in choosing sites.

The financial question for residents is who pays for that infrastructure. New generation and transmission may be funded by project developers, utilities, customers, taxpayers or a combination. The Milam County plan emphasizes protecting Texas ratepayers, and the Michigan project also includes a commitment that local ratepayers should not bear the campus’s infrastructure costs. Those commitments reduce a stated risk, but they do not independently prove that households will face no indirect costs through taxes, utility planning, transmission charges or public incentives.

Rank #4
NavePoint 12U Server Rack Enclosure with Glass Door, Cooling Fan, Locks, & Removable Side Panels - 12U Wall Mount Network Cabinet 19 Inch Rack 17.7" Deep (450mm)
  • DURABLE BUILD: Constructed from high-quality Cold Rolled Steel, the NavePoint Consumer Series 12U network cabinet boasts a sturdy, welded frame. Fitting EIA standard 19” networking equipment, this server cabinet confidently supports up to 110 lbs, providing a resilient base for your vital IT gear and equipment
  • CONVENIENT DESIGN: This 12U cabinet features a reinforced, heat-treated, tempered glass front door with a security lock. Perfect for applications requiring both security and accessibility, its compact design of 17.72"L x 21.65"W x 24.42"H offers a practical solution for space-constrained settings.
  • EASY & CUSTOMIZABLE EQUIPMENT SET UP - The 12U IT cabinet, with removable side panels and security locks, offers customization at its finest. Whether it's for an efficient device or cable management, this data cabinet ensures secure, adaptable configurations that suit your networking server requirements
  • ENHANCED VENTILATION & SECURITY - Built-in fans and flow-through ventilation work to prevent overheating, ensuring optimal operation of your equipment. The reinforced, lockable tempered glass front door not only boosts security but also facilitates easy monitoring of installed equipment.
  • SAFETY & COMPLIANCE - All NavePoint products are built to industry standards.

Jobs and wages

OpenAI estimated that the five-site announcement would create more than 25,000 onsite jobs and tens of thousands of additional jobs across the United States. These are company estimates and may include construction, operations and related activity. They should not be confused with permanent jobs at each campus.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

The broader Oracle partnership carried a separate estimate of more than 100,000 jobs across construction, operations, manufacturing and local services. In Michigan, Oracle said more than 700 tradespeople were working on the campus as of June 1, 2026. Construction employment can be substantial but temporary; the number, pay and skill mix of permanent data-center jobs will vary by site.

Water, land and community impacts

Cooling can make water demand an important local issue. The Milam County announcement specifically says the site was designed to minimize water use. That does not establish a common cooling design across the five sites or the wider Stargate portfolio.

Residents may also care about land use, noise, construction traffic, local tax incentives, housing demand, industrial-service jobs and the effect of new transmission infrastructure. A project can bring construction spending and tax revenue while still creating costs that are distributed unevenly across a community.

The main risks to the buildout

  1. Power availability: A site can be announced before generation and transmission are ready.
  2. Permitting and community support: Zoning, environmental reviews and local opposition can affect schedules.
  3. Financing: A multiyear commitment still depends on project-level capital, contracts and credit conditions.
  4. Chip supply: Planned capacity depends on obtaining large volumes of advanced accelerators and networking equipment.
  5. Construction: Specialized electrical, cooling and high-density data-center work can face labor and supply-chain constraints.
  6. Technology changes: New accelerator generations and higher rack densities may require retrofits, even if a facility is designed for flexibility.
  7. Customer concentration: Stargate relies on OpenAI demand and a relatively small group of infrastructure, energy and financing partners.
  8. Operating economics: A campus designed for a maximum load may not run at that level continuously, affecting utilization and returns.

How to judge future Stargate updates

When a company announces another gigawatt or another campus, ask which stage the figure represents:

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
  • Announced: A location and intention have been publicly identified.
  • Contracted or financed: Agreements and funding commitments exist, though terms may vary.
  • Under construction: Physical work has begun, but the facility may be years from operation.
  • Energized: The site has access to electrical power.
  • Operational: Servers are installed and workloads are running.
  • At scale: The campus is operating near its stated usable capacity.

This framework prevents the common mistake of treating a planned gigawatt as an operating data center or treating a long-term investment target as money already spent.

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.

Leave a Reply

Your email address will not be published. Required fields are marked *

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

More post from the Money Desk

  1. The Money DeskBlogTheFinanceBase09 OCT 267 minMortgage Escrow FAQs: Taxes, Insurance, Shortages, and Refunds
  2. The Money DeskBlogTheFinanceBase09 OCT 265 minHow Mortgage Escrow Accounts Work and What Homeowners Pay For
  3. The Money DeskBlogTheFinanceBase09 OCT 265 minHow to Read a Stock Chart, Volume and Market-Cap Data
Recommended PC Tool
Recommended PC Tool
Outdated Drivers Are Slowing You DownFree scan - exact matches
PC Slower Than It Used to Be?Free scan - under a minute

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.