Microsoft Project is worth buying when you need formal schedule control, dependencies, baselines, critical-path analysis, resource planning, or the installed Project desktop app. It is usually excessive for simple task lists. The decision is also more complicated in 2026: Microsoft is incorporating Project for the web into Planner, while Project Online is scheduled to retire on September 30, 2026.
For most professional users who specifically need Microsoft Project, Planner and Project Plan 3 is the most practical current option. Teams that only need browser-based planning should consider Planner Plan 1; teams needing simple collaboration may already have enough with Microsoft Planner included in an eligible Microsoft 365 subscription.
As an Amazon Associate I earn from qualifying purchases.
What is Microsoft Project in 2026?
“Microsoft Project” now describes a family of related products rather than one single application:
PC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11Outdated Drivers Are Slowing You Down
One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware match| Product | What it does | Current position |
|---|---|---|
| Project desktop | Installed Windows application for detailed schedules, dependencies, baselines, resources, costs and critical paths. | Still relevant, particularly for advanced schedulers. |
| Project for the web | Browser-based project management built on Microsoft Power Platform and Dataverse. | Being incorporated into Microsoft Planner. Microsoft says most capabilities will continue in the new Planner experience. |
| Microsoft Planner | Collaborative task and work-management application. | Microsoft’s strategic destination for the web-based experience. |
| Project Online | SharePoint-based cloud project and portfolio-management service. | Scheduled for retirement on September 30, 2026. |
| Project Server Subscription Edition | Server-based enterprise project-management option. | Relevant mainly to organizations requiring a controlled server deployment. |
Microsoft’s explanation of the product family is available in its Project for the web overview. The key distinction is that Project desktop is scheduling-centric, while Planner is collaboration-centric. Microsoft is bringing the web experiences closer together, but Planner is not simply Project desktop in a browser.
#1 Best Overall
- ProjectLibre key features: Compatibility with Microsoft Project 2010
- User Interface improvement
- Gantt Chart & PERT Chart
- Network Diagram
- Earned Value Costing
Microsoft Project pricing
The following are U.S. price signals shown by Microsoft on August 18, 2026. Prices are per user per month with annual payment, may exclude tax, and can vary by region, billing term, subscription status and Microsoft 365 eligibility.
| Plan | Listed price | Best for | Important qualification |
|---|---|---|---|
| Microsoft Planner | Included with eligible Microsoft 365 subscriptions | Basic collaborative task management. | Included features depend on the Microsoft 365 subscription. |
| Planner Plan 1 Formerly Project Plan 1 |
$10 per user/month, paid yearly | Browser-based project planning. | Does not include the full Project desktop application. |
| Planner and Project Plan 3 Formerly Project Plan 3 |
$30 per user/month, paid yearly | Professional scheduling and Microsoft integration. | Includes Project desktop and Project Online access during the transition period. |
| Planner and Project Plan 5 Formerly Project Plan 5 |
$55 per user/month historically listed | Enterprise portfolio and resource management. | Microsoft says it entered end of sale on May 1, 2026. Verify availability before considering it for a new purchase. |
Check Microsoft’s current Planner pricing page before buying. Annual subscriptions typically auto-renew, and the per-user price is only part of the cost. Also account for Microsoft 365 licensing, collaborator access, implementation, training, integrations and—if applicable—migration from Project Online.
What makes Plan 3 cost more?
Plan 1 is primarily a premium web-planning license. Plan 3 adds the installed Project desktop client and more formal project-control capabilities, including baselines, critical paths, advanced dependencies with lead and lag, resource-request features, program management, financials, budgeting and costing.
Recommended Free Tools
Not every project participant necessarily needs a full license. Before purchasing, separate users who build and maintain schedules from people who only view updates, complete tasks or collaborate in Teams. Microsoft’s licensing rules and role requirements should be checked for the specific deployment.
Microsoft Project features
Scheduling and project planning
Microsoft Project is strongest when a project needs a structured schedule rather than an unstructured list of tasks. Depending on the product and plan, it supports:
- Work breakdown structures and hierarchical task lists.
- Task durations, milestones, start dates and finish dates.
- Task constraints and predecessor relationships.
- Finish-to-start and other dependency relationships.
- Lead and lag in higher-tier configurations.
- Automatically scheduled or dynamically calculated tasks in the web experience.
- Grid, board, timeline, chart and Gantt-style views.
- Critical-path analysis.
- Baselines for comparing the approved plan with current performance.
- Roadmaps and cross-project visibility where supported.
These features are valuable in construction, engineering, IT delivery, operations and other work where a delay in one activity affects many downstream activities.
Resources, capacity and costs
Project can go beyond assigning a person to a task. Higher-level configurations are designed for organizations that need to consider shared resources, capacity, requests and competing projects. Depending on the plan and environment, capabilities may include:
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
Rank #2
- Assigning people or teams to tasks.
- Resource requests and engagements.
- Capacity and allocation planning.
- Resource pools shared across projects.
- Budgeting, financials and project costing.
- Portfolio prioritization and program management.
- Enterprise-level resource management and reporting.
There is an important difference between basic resource assignment and true portfolio resource management. A team assigning owners to tasks does not necessarily need an enterprise portfolio product. Conversely, a PMO managing scarce engineers across dozens of projects may quickly outgrow a basic Planner setup.
Collaboration and Microsoft 365 integration
Microsoft Project and Planner fit naturally into organizations already using Microsoft 365. Relevant capabilities include:
- Microsoft Teams integration.
- Shared plans and task assignments.
- Comments, file attachments and collaborative updates.
- Microsoft identity, permissions, administration and compliance controls.
- Power Automate and Power Platform integration where licensed.
- Dataverse storage for Project for the web data.
Project desktop remains less collaboration-oriented than browser-first tools. It is well suited to a project manager carefully modeling a schedule, while Planner is better for a wider team that needs to see, update and discuss work together.
Reporting and analytics
Project environments can support dashboards, status reporting, progress tracking, baseline-versus-current comparisons, portfolio views and Power BI reporting. However, feature availability varies by plan and configuration. Microsoft’s service description contains the plan-specific feature qualifications.
Plan-by-plan review
Microsoft Planner: best for simple coordination
Included Planner is a sensible starting point for teams coordinating ordinary work: assign tasks, add due dates, organize a board and collaborate in Microsoft 365.
It is a poor fit when you need formal baselines, critical-path analysis, complex dependencies, detailed cost control, or resource-constrained portfolio planning. In those situations, upgrading to a premium plan—or choosing another platform—may be more economical than forcing a simple task tool to behave like a scheduling system.
Planner Plan 1: best for browser-based project planning
Plan 1 is appropriate for teams that want more than basic Planner but do not need the desktop Project client. Microsoft lists project goals, backlogs and sprints, reports and dashboards, customization, dependencies, and grid, board, timeline and chart views among its capabilities.
Rank #3
It is a good match for smaller professional projects and browser-first teams. Its central limitation is that it should not be described as the complete Project desktop experience online. Users who need deep schedule modeling, baselines, critical-path work, financial controls or the installed client should examine Plan 3 instead.
Planner and Project Plan 3: the practical professional choice
Plan 3 is the clearest choice for many organizations that mean “Microsoft Project” in the traditional sense. Microsoft lists the following additions to the Plan 1 experience:
- Project desktop.
- Task history.
- Roadmaps.
- Baselines and critical path.
- Advanced dependencies with lead and lag.
- Resource requests.
- Program-management capabilities.
- Project financials, budgeting and costing.
- Project Online access during the transition period.
It is particularly suitable for engineering, construction, operations, IT and PMO teams that need structured schedules while retaining Teams and Microsoft 365 integration.
Planner and Project Plan 5: do not assume it is available
Plan 5 was historically aimed at enterprise portfolio prioritization, resource allocation and governance. However, Microsoft says it moved to end of sale on May 1, 2026. The historically displayed $55 price should therefore not be treated as a normal new-purchase recommendation. Existing customers, renewals and partner availability may be handled differently; confirm the live purchasing path and any replacement offered by Microsoft.
Project desktop versus Planner
| Your need | Better starting point |
|---|---|
| Simple task lists and team coordination | Microsoft Planner |
| Collaborative boards and shared task updates | Microsoft Planner |
| Browser-based Gantt-style planning and dependencies | Planner Plan 1 or higher |
| Detailed schedule modeling | Project desktop |
| Baselines and critical-path analysis | Plan 3 or an applicable desktop/online configuration |
| Formal cost and budget tracking | Plan 3 or a higher-level configuration |
| Resource requests and program management | Plan 3 or an enterprise configuration |
| Portfolio prioritization and enterprise resource allocation | Historically Plan 5; verify the current replacement |
| Existing Project Online deployment | Begin transition planning immediately |
Project desktop is the better tool for schedule engineers and project controls specialists. Planner is easier for broad participation and day-to-day collaboration. The right choice may be a combination: a smaller number of Plan 3 users maintaining the schedule and a larger group using Microsoft 365 collaboration tools.
Free tools Windows power users keep installed
One-click scans. No signup required.
Project Online retirement: what existing customers need to know
Important: Microsoft says Project Online will retire on September 30, 2026. Project Online-only SKUs stopped being sold to new customers on October 1, 2025, and Microsoft’s comparison information says creation of new Project Web App sites will be blocked from April 1, 2026.
Organizations with Project Online should not start a new long-term deployment there. Microsoft recommends a transition approach in which customers complete existing projects in Project Online while starting suitable new work in Project for the web or Planner. The correct destination depends on project complexity, customizations, integrations, data size, reporting and portfolio requirements.
Rank #4
- Designed for Your Windows and Apple Devices | Install premium Office apps on your Windows laptop, desktop, MacBook or iMac. Works seamlessly across your devices for home, school, or personal productivity.
- Includes Word, Excel, PowerPoint & Outlook | Get premium versions of the essential Office apps that help you work, study, create, and stay organized.
- 1 TB Secure Cloud Storage | Store and access your documents, photos, and files from your Windows, Mac or mobile devices.
- Premium Tools Across Your Devices | Your subscription lets you work across all of your Windows, Mac, iPhone, iPad, and Android devices with apps that sync instantly through the cloud.
- Easy Digital Download with Microsoft Account | Product delivered electronically for quick setup. Sign in with your Microsoft account, redeem your code, and download your apps instantly to your Windows, Mac, iPhone, iPad, and Android devices.
Project Online uses a SharePoint-based data store, while Project for the web uses Dataverse. That difference means migration is not automatically a one-to-one transfer. Custom fields, workflows, reports, integrations, add-ons and custom code can all increase the effort and risk. Microsoft says its native migration tools are best suited to standard deployments without custom code or integrations.
Project Online migration checklist
- Inventory active and archived projects.
- Classify projects by complexity and business criticality.
- Document custom fields, workflows, reports, integrations and third-party add-ons.
- Identify users who need Project desktop, premium Planner or collaborator-only access.
- Export and back up project data before major changes.
- Pilot a representative project in the proposed Planner environment.
- Compare dependencies, schedule behavior, resources, reporting and permissions.
- Decide whether Planner, Project Server Subscription Edition or a third-party PPM platform is the better destination.
- Set an internal cutoff well before September 30, 2026.
- Train users on the new product names and workflows.
Microsoft Project pros and cons
Pros
- Mature concepts for formal project scheduling.
- Detailed dependency, milestone and critical-path support.
- Baselines and progress comparisons in applicable plans.
- Installed Project desktop client for advanced users.
- Microsoft Teams, Power Platform, Dataverse and Microsoft 365 integration.
- Resource, financial and portfolio capabilities in higher-tier configurations.
- Enterprise identity, administration, security and compliance options.
Cons
- Confusing product names and overlapping experiences.
- Project Online’s imminent retirement creates migration pressure.
- Advanced capabilities require more expensive and changing license tiers.
- Project desktop is Windows-centric and less collaborative than browser-first products.
- It can be excessive for basic task tracking.
- Migration may be difficult for heavily customized Project Online environments.
- Some organizations may need specialist portfolio, resource or collaboration tools.
Microsoft Project alternatives
Asana
Asana is a strong alternative for cross-functional teams in marketing, operations, product and knowledge work. It emphasizes usability, goals, portfolios, workload, forms, approvals, proofing and reporting.
Asana’s listed U.S. signals include a free Personal plan for up to two users, Starter at $10.99 per user per month billed annually ($13.49 monthly), and Advanced at $24.99 annually. Enterprise pricing is custom. It is generally less suited to the deepest traditional schedule-engineering requirements than Project desktop.
monday.com
monday.com is a flexible, visual work-management platform with boards, dashboards, automations, integrations and Gantt views. Its displayed starting signals include a free plan for up to two seats, Basic at $9 per seat per month annually and Pro at $19 annually. Paid plans start at three users, and displayed prices vary by product and team-size selector.
It is attractive when customizable workflows matter more than traditional scheduling conventions. It may require substantial configuration for strict work-breakdown structures or sophisticated resource scheduling.
Smartsheet
Smartsheet is a natural candidate for spreadsheet-oriented PMOs moving beyond Excel. It combines grid-based planning with automation, dashboards and reporting. Use its live pricing selectors for current figures; the available source does not support a responsible fixed price here.
ClickUp
ClickUp combines tasks, documents, dashboards, whiteboards, goals, time tracking and customizable workflows. It suits buyers seeking broad all-in-one coverage, but that flexibility can create configuration and governance work. Verify current tiers directly before purchase.
Best Value
Jira
Jira is the strongest alternative in this list for software-development teams that need issue tracking, backlogs, sprint planning and agile workflows. Atlassian provides a live pricing calculator. Jira is usually a poor fit for construction, engineering or capital projects centered on traditional schedules, resource loading, baselines and cost controls.
Which project-management tool should you choose?
- Choose included Planner if you need basic task coordination and already have eligible Microsoft 365 licenses.
- Choose Planner Plan 1 if you want browser-based dependencies, timelines, reports, goals, backlogs and sprints without Project desktop.
- Choose Plan 3 if you need formal scheduling, baselines, critical paths, advanced dependencies, costs, resources or the installed desktop client.
- Choose an alternative if ease of adoption, visual collaboration or specialized agile workflows matter more than traditional schedule control.
- Choose Project Server or specialist PPM software only after assessing whether Planner can replace the specific enterprise capabilities you use today.
For a Microsoft 365 organization, Plan 3 is the most defensible default for professional project managers—but not automatically the cheapest. Calculate the number of schedule authors, desktop users, collaborators and administrators, then include migration and implementation costs. For a small team tracking ordinary work, included Planner or Plan 1 is likely to provide better value.
Frequently Asked Questions
Is Microsoft Project the same as Microsoft Planner?
No. Microsoft Planner is primarily collaboration and task management, while Project desktop remains focused on detailed schedule modeling. Microsoft is incorporating Project for the web into Planner, but that does not make Planner identical to the desktop application.
Quick wins for a faster PC:
Scan for outdated or missing drivers - takes under a minuteDriver Scan →Clear out junk files and repair common Windows errorsFree Scan →Fix the driver behind crashes, sound loss and screen glitchesFind Drivers →Which Microsoft plan includes Project desktop?
Microsoft’s current Planner and Project Plan 3 subscription includes the installed Project desktop client. Confirm the current license terms and operating-system requirements before purchase.
Is there a free version of Microsoft Project?
There is no general free version of the full Project desktop application. Basic Microsoft Planner may be included with eligible Microsoft 365 subscriptions, but its capabilities are more limited.
Does Microsoft Project work on a Mac?
Do not assume the full desktop experience is natively equivalent on macOS. Check Microsoft’s current requirements and consider the browser experience or an approved remote-access method for Mac users.
Quick Recap
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.
The Tool Desk
Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →