OGDCL’s board approved a USD 715 million commitment for Phase 1 of the Reko Diq project on August 18, 2025, and shareholders endorsed the investment on September 10, 2025. The commitment includes project financing costs; it is not the same as the company’s expected cash contribution. OGDCL said expected shareholder contributions would be USD 391 million after accounting for financing anticipated from the project company.
What did OGDCL approve?
The USD 715 million is OGDCL’s pro-rata Phase 1 commitment, including project financing costs. OGDCL separately estimated that its shareholder contributions would total USD 391 million after taking into account financing expected to be secured by Reko Diq Mining Company (RDMC), the project company. The commitment may be adjusted for actual financing costs and inflation. OGDCL’s August 2025 disclosure described both figures.
On September 10, 2025, OGDCL shareholders endorsed increasing the investment in Pakistan Minerals (Private) Limited (PMPL) through equity, shareholder loans, or both, to fund PMPL’s share of Phase 1 expenditures. The extraordinary general meeting notice estimated project financing of up to USD 3.5 billion. That project-level financing estimate is distinct from OGDCL’s commitment and expected shareholder contribution. The meeting notice was hosted by the Pakistan Stock Exchange.
How does the commitment relate to project debt?
The financing distinction matters: USD 715 million is the stated commitment with financing costs included, while USD 391 million is the expected shareholder contribution after anticipated project-company financing. The two amounts answer different questions and should not be treated as interchangeable cash requirements.
The Tool Desk
Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →#1 Best Overall
- Authentic tipple for steam or diesel eras
- Typical of coal loaders across the us
- Conveyor & supports for above- or below-ground operations
- Finely detailed "corrugated metal" Construction
- Separate windows, walkway & stairs
OGDCL’s board also approved related financing agreements, including an SOE Completion Agreement and a Transfer Restrictions Agreement. Under the completion agreement, the three Pakistani state-owned enterprises (SOEs) collectively guarantee their pro-rata contributory share of RDMC’s secured debt until financial completion. This is a guarantee tied to the SOEs’ share, not a statement that OGDCL alone guarantees all project borrowing.
Who owns and operates Reko Diq?
| Shareholder or group | Project interest | Role |
|---|---|---|
| Barrick Gold | 50% | Management and operatorship rights |
| OGDCL, Pakistan Petroleum Limited and Government Holdings (Private) Limited | 25% collectively, divided equally | Pakistani state-owned enterprise stake; PMPL manages the SOEs’ shareholding |
| Government of Balochistan | 25% | Government shareholder |
OGDCL’s 8.33% interest is one-third of the SOEs’ combined 25% share. Its USD 715 million commitment is therefore OGDCL’s pro-rata commitment, not the cost of the entire mine. OGDCL’s business-development information describes the ownership structure.
Rank #2
- Dual-Mode High Banker Gold Sluice: Manually switch between sluice mode and highbanker setup. The highbanker mode handles larger batches efficiently, while the sluice mode suits shallow water and small streams, meeting different panning needs.
- 26-Piece Complete Set: From collecting and screening to refining and storage, this portable mining equipment kit includes tools for the entire gold panning process and is ready to use right out of the box
- Aluminum Frame: Built with a lightweight, long-lasting aluminum frame that resists wear, pressure, and rust, this highbanker sluice box is designed to handle demanding outdoor mining conditions for extended service life.
- Efficient Recovery: The dual-layer miner's moss and carpet in the gold sluice box kit capture fine gold down to 50 mesh, with up to 98.7% recovery. The angled mesh and large riffle optimize water flow for fast separation of sand, gravel, and heavy metals
- Portable Design: The foldable construction reduces packed size by over 50%. Secure-grip shoulder straps and a dual drawstring backpack make storage and carrying easy, making this highbanker gold panning kit ideal for hiking and road trips
What is planned for the mine?
The following figures come from OGDCL’s 2025 reporting of the updated feasibility study. They are plans and estimates, not guaranteed outcomes or a confirmed current timetable. OGDCL’s 2025 feasibility announcement reported the project scale and production estimates.
| Measure | 2025 feasibility-study figure | Qualification |
|---|---|---|
| Phase 1 capital outlay | USD 5.6 billion | Excludes financing costs and inflation |
| Phase 1 processing | 45 million tonnes per annum | Planned mill-feed processing from 2028 |
| Phase 2 processing | 90 million tonnes per annum | Planned capacity by 2034, doubling processing |
| Mine life | 37 years | Feasibility-study estimate |
| Life-of-mine production | 13.1 million tonnes of copper and 17.9 million ounces of gold | Expected production on a 100% project basis, based on existing reserves |
OGDCL also said in 2025 that the financing level had risen to USD 3.5 billion from USD 3.0 billion, increasing financing costs. It said the project remained economically viable under revised assumptions. Those financing figures do not replace the USD 5.6 billion Phase 1 capital estimate, which excludes financing costs and inflation. The financing update was reported in OGDCL’s 2025 disclosure.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
Rank #3
- BUILD YOUR OWN ENGINE – Assemble a clear 4-cylinder engine model kit with 175+ durable pieces. A fun DIY engineering toy engine that shows how pistons, valves, and gears really move.
- WORKING MODEL ENGINE – Install 3 AA batteries (not included), press start, and see this visible engine model kit come to life as pistons, valves, and gears move just like a real car engine.
- COMPLETE STEM ACTIVITY KIT – This kids engine build kit includes everything needed: 175+ parts, tools, illustrated instructions, and a Learning Guide for an engaging STEM toy experience.
- FUN & EDUCATIONAL – Encourages problem-solving skills and curiosity while teaching kids about mechanics and engineering. Perfect model engine kit for young builders and hobby kits for boys and girls.
- GREAT STEM GIFT – An exciting engine building kit for kids who love cars, building toys, and model kits. Inspires creativity and discovery through hands-on STEM play!
When is production expected to start?
The updated feasibility-study plan cited by OGDCL in 2025 envisioned Phase 1 processing from 2028 and Phase 2 capacity by 2034. These are dated planning targets, not confirmation that production will begin on those dates.
In its April 2026 report, OGDCL said that since February 2026 the operator had continued reviewing security arrangements, the development timetable, financing and the capital budget. That report establishes the status at the time it was issued; it does not establish whether the review later concluded or what schedule is authoritative as of October 2026. A newer company or project filing is needed to confirm the current timetable. See OGDCL’s April 2026 report.
Quick Recap
Best Value
- FOR BASIC TEACHING TO ADVANCED SCIENCE: 444 pieces molecular model kit, including 136 atoms, 158 bonds and 150 parts for Carbon-60(Fullerene), provides to students from Grade 7 to Graduate level.
- TWO CHEMICAL STRUCTURE MODELS: The ball-and-stick models use spheres to represent atoms and sticks to represent chemical bonds. In the space-filling model, the spheres are drawn to scale and are next to one another as atoms are in real molecules.
- CHEMISTRY EDUCATIONAL MOLECULE MODEL IN 3D: It can display chemical structure, molecular bond, and bond angle in all directions. Demonstrate fundamental molecular geometry, chemical molecular structure, stereochemistry with 3D modeling studies.
- EASY TO LEARN: The universal standard adopted for each atom's color makes it easier for you to use and learn. Atoms and chemical bonds combine tightly and firmly and can be easily disassembled by disconnecting tools.
- If you’re not in love with it for whatever reason, we’ll give you a full replacement or refund—no questions asked. If you have any doubt, please tell us. With nothing to worry about, or even to share with your friends, try it now.
Rank #4
- All-in-One Model Tool Kit: The complete model tool kit is suitable for a beginner, hobbyist and advanced modeler as well, you can use it to assemble a variety of model kits, like cars, robots, ships, planes and other craft model
- Full Range of Tools and Cost Efficient: The model basic tools kit includes cutting pad, side pliers, tweezers, craft cutter and replacement cutter, double-sided polished bar, file, manual grinding machine, screwdriver, bits, hand drill, etc. A complete set of essential model building tools for plastic model projects
- Premium Quality: each tool in this hobby model building tools kit is made of high quality materials, sturdy and durable. The craft cutter comes with a safety cap. The side pliers are made of carbon steel, high hardness and good durability
- Practical Model Kit Tools For All Skill Levels: Designed for beginners, hobbyists and experienced builders, these model making tools are compact, lightweight and easy to handle. The included cutting mat provides a dedicated work surface, making this set a practical choice for detailed plastic model assembly and finishing
- Great Gift for Model Lovers: Ideal for building and maintaining plastic robots model, cars model, aircraft model, ships model, miniatures and other hobby model kits, making it a practical gift for model makers and DIY craft enthusiasts, or you can use the model tools kit to building a model gift for your friend and family
How to compare the headline commitment with other Reko Diq figures
- Check the scope: USD 715 million is OGDCL’s commitment, while USD 5.6 billion is the estimated Phase 1 capital outlay for the project.
- Check financing costs: OGDCL’s commitment includes them; the USD 5.6 billion Phase 1 estimate excludes financing costs and inflation.
- Check the assumed project debt: the USD 391 million figure is the expected shareholder contribution after anticipated project financing, rather than the full commitment.
- Check the date and status: the board approval was in August 2025, shareholder endorsement followed in September 2025, and the operator review was reported in April 2026.
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.