Intel’s Ohio One semiconductor campus is still being built in New Albany, Ohio, but its first fab is now expected to begin operating in 2030 or 2031—roughly five to six years after the project’s original 2025 production target. No cited source identifies inclement weather as the cause of the latest delay. Intel has instead described a slower construction pace and flexibility tied to customer demand and business conditions.
When is Intel’s Ohio fab expected to open?
Intel’s February 28, 2025 schedule distinguishes construction completion from the start of operations. The dates below are Intel’s stated expectations, not confirmed opening dates.
| Project stage | Construction completion | Operations expected to start |
|---|---|---|
| Mod 1 | 2030 (Intel, February 28, 2025) | 2030–2031 (Intel, February 28, 2025) |
| Mod 2 | 2031 (Intel, February 28, 2025) | 2032 (Intel, February 28, 2025) |
That is a substantial change from Intel’s January 2022 announcement, which targeted production beginning in 2025. Comparing the original production target with the current Mod 1 operations window puts the expected start roughly five to six years later. Construction completion and production are separate milestones, so a completed building would not, by itself, mean the fab had opened for operations.
Did inclement weather cause the delay?
Weather has not been established as the reason for the current schedule. Intel’s February 2025 update attributed its approach to completing the project in a financially responsible way and said the company would continue construction at a slower pace, with the ability to accelerate if customer demand warranted it. The August 26, 2026 WOSU/WYSO report likewise described slower but continuing work and deadlines that could shift with demand; it did not identify weather as the cause.
Crashes, No Sound, or Screen Glitches?
Random freezes, missing sound and display glitches usually trace back to one bad driver. Find and replace yours safely.Free scan · under a minutePC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11#1 Best Overall
- Next‑Gen Platform Support: Compatible with Intel 800 Series Chipset‑based motherboards with LGA1851 Socket enabling PCIe 5.0/4.0 and high‑speed DDR5 memory (up to 7200 MT/s).
- High‑Performance Core Configuration: Features up to 24 cores (8 P‑cores + 16 E‑cores) for demanding gaming and creator
- Ultra‑Fast Boost Clocks: Reaches up to 5.5 GHz max turbo frequency for top‑tier responsiveness and performance
- Built for Enthusiasts: Unlocked for performance tuning when paired with Intel Z‑series chipsets, making it ideal for overclockers and power users.
- Robust Power & Thermal Design: Engineered with 125W base power and 250W max turbo power to sustain high‑intensity
Intel executive Naga Chandrasekaran said the company was taking “a prudent approach” to complete Ohio One responsibly and set it up for long-term success. He also said Intel would retain flexibility to accelerate construction and operations if demand warranted. Those statements support demand and business alignment as the clearest publicly described factors; they do not establish that weather played no role in any individual construction decision.
Is Ohio One still being built?
Yes. The available status reports describe an active project, not a canceled one. In August 2026, local reporting said work remained underway, although at a slower pace, and Intel still described the first fab as on track for completion by 2031. New Albany’s municipal construction page says Intel has reiterated its full commitment and lists related infrastructure work in 2026.
Rank #2
- Game Without Compromise. Play harder and work smarter with Intel Core 14th Gen processors
- 20 cores (8 P-cores plus 12 E-cores) and 28 threads. Integrated Intel UHD Graphics 770 included
- Up to 5.6 GHz with Turbo Boost Max Technology 3.0 gives you smooth game play, high frame rates, and rapid responsiveness
- Compatible with Intel 600-series (with potential BIOS update) or 700-series chipset-based motherboards
- DDR4 and DDR5 platform support cuts your load times and gives you the space to run the most demanding games
Ohio One is planned as a two-fab semiconductor campus in New Albany, Licking County. Intel describes the project as an investment of more than $28 billion. That figure is the stated project investment, not a measure of spending completed to date.
What work has already been reported?
In February 2025, Intel reported more than 6.4 million work hours and more than 200,000 cubic yards of concrete for the Ohio project. These are progress figures reported by Intel at that time; they do not change the later schedule or establish a date when production will begin.
Do these 3 things before closing this tab:
1Fix the driver behind crashes, sound loss and screen glitches2Repair Windows errors before they cause bigger problems3Scan for outdated or missing drivers - takes under a minuteRank #3
- Get ultra-efficient with Intel Core Ultra desktop processors that improve both performance and efficiency so your PC can run cooler, quieter, and quicker.
- Core and Threads 24 cores (8 P-cores plus 16 E-cores) and 24 threads. Integrated Intel Graphics included
- Performance Hybrid Architecture Integrates two core microarchitectures, prioritizing and distributing workloads to optimize performance
- Performance Unlocked Up to 5.7 GHz unlocked. 40MB Cache
- Compatibility Compatible with Intel 800 series chipset-based motherboards
What the revised dates mean for Ohio
The schedule points to a longer wait for production, not a confirmed abandonment of the campus. For local workers, suppliers and public agencies planning around the project, the distinction between construction milestones and operating production dates matters: Intel’s current schedule places the first fab’s operations in 2030–2031, while its second fab is expected to begin operating in 2032. The company has left room to adjust that pace in response to demand.
Quick Recap
Best Value
- Game without compromise. Play harder and work smarter with Intel Core 14th Gen processors
- 24 cores (8 P-cores plus 16 E-cores) and 32 threads. Integrated Intel UHD Graphics 770 included
- Leading max clock speed of up to 6.0 GHz gives you smoother game play, higher frame rates, and rapid responsiveness
- Compatible with Intel 600-series (with potential BIOS update) or 700-series chipset-based motherboards
- DDR4 and DDR5 platform support cuts your load times and gives you the space to run the most demanding games
Rank #4
- Game Without Compromise. Play harder and work smarter with Intel Core 14th Gen processors
- 20 cores (8 P-cores plus 12 E-cores) and 28 threads. Discrete graphics required
- Up to 5.6 GHz with Turbo Boost Max Technology 3.0 gives you smooth game play, high frame rates, and rapid responsiveness
- Compatible with Intel 600-series (with potential BIOS update) or 700-series chipset-based motherboards
- DDR4 and DDR5 platform support cuts your load times and gives you the space to run the most demanding games
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.