Equinix’s May 5, 2016 expansion report described planned projects in Silicon Valley, the New York metro area and Hong Kong. The New York-market project was NY5 Phase II in Secaucus, New Jersey—not a data center in New York City. The report estimated about $200 million in investment, 200,000 square feet and capacity for roughly 4,000 server cabinets, but its project count is internally inconsistent: it first describes three projects, then refers to four.
What Equinix announced in 2016
The May 2016 report covered three market initiatives: a new Silicon Valley facility, an expansion at the NY5 campus serving the New York metro, and growth in Hong Kong. These were part of Equinix’s wider 2016 construction push, which also included projects in Dallas, São Paulo, Tokyo, Sydney, Amsterdam, Northern Virginia, Atlanta, Dublin, Frankfurt and Warsaw. The original report’s aggregate figures—about $200 million, 200,000 square feet and 4,000 cabinets—are estimates attributed to that report, not a consistent project-by-project accounting. Data Center Knowledge’s May 5, 2016 report
How the projects compare
Equinix’s 2016 year-end construction table gives named phases, target openings, cabinet capacities and estimated capital expenditure. These are planned values in the company’s filing, not proof that each phase opened on schedule. SV10’s cabinet figure differs between the filing and later opening announcement because the figures describe different points in the build-out.
| Market and project | Location | Target opening in 2016 year-end filing | Planned cabinets | Estimated capex |
|---|---|---|---|---|
| SV10 Phase I | San Jose, California | Not stated in the cited filing summary | 795 sellable cabinets | $125 million |
| NY5 Phase II | Secaucus, New Jersey | Q2 2017 | 1,200 sellable cabinets | $76 million |
| HK1 Phase X/XI | Hong Kong | Q1 2017 | 515 sellable cabinets | $16 million |
| HK2 Phase IV | Hong Kong | Q1 2017 | 900 sellable cabinets | $39 million |
Source for the project-level figures and target dates: Equinix’s 2016 annual report. The filing lists a broader construction pipeline and two Hong Kong phases, so its estimates should not be mechanically added and treated as the same scope as the news report’s approximate $200 million total.
Free tools Windows power users keep installed
One-click scans. No signup required.
#1 Best Overall
- Save valuable floor space: 6U wall mount server cabinet Dimensions: 13.78" H x21.65" W x17.72" D.Maximum mounting depth is 14.2"
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access. Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punch-out panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
Silicon Valley: SV10 extended an established campus
SV10 was planned for an 11-acre site adjacent to Equinix’s SV1 and SV5 facilities at its Great Oaks campus in San Jose. Equinix announced an approximately $125 million investment in the first phase. The location mattered because Silicon Valley was a high-demand, land-constrained data-center market; Equinix said limited capacity could restrict growth unless new supply came online. Building beside existing facilities also supported the company’s interconnection proposition: customers could connect across a dense campus ecosystem rather than simply rent isolated floor space. Equinix’s SV10 groundbreaking announcement
Phase one and the longer build-out
When Equinix announced SV10’s opening in 2017, it described the initial phase as more than 37,000 square feet of colocation space with room for 930 cabinets. The same announcement described a three-phase full-build plan for 2,820 cabinets. The opening figure is a later description of the initial phase; it is not interchangeable with the 795 sellable cabinets shown for SV10 Phase I in the year-end construction table. Equinix’s SV10 opening announcement
New York metro: NY5 Phase II was in Secaucus
NY5 is a New Jersey campus serving the New York market. Its Phase II expansion was in Secaucus, not New York City—a distinction that matters for anyone assessing local real estate, permitting or network geography. The 2016 report said NY5’s first phase comprised four buildings, had capacity for more than 10,000 cabinets and was about 85% full when the expansion was discussed.
Rank #2
- Save valuable floor space: 12U wall mount server cabinet Dimensions: 24.25" H x21.65" W x17.72" D. MAXIMUM MOUNTING DEPTH is 14.2".
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access; Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punchout panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
Equinix linked demand to financial-services customers, hybrid-cloud adoption and BATS Global Markets’ move of trading platforms to the campus. Those are the company’s and report’s explanations of market demand, not an independently measured breakdown of the expansion’s causes. The New Jersey site offered access to the New York financial and enterprise market while locating the facility outside the city’s boundaries. The 2016 year-end filing put NY5 Phase II at 1,200 sellable cabinets, an estimated $76 million in capex and a Q2 2017 target opening.
Hong Kong: the announcement does not name one definitive phase
The May 2016 report described a Hong Kong expansion but did not clearly identify a facility phase. Equinix’s year-end construction table separately listed HK1 Phase X/XI and HK2 Phase IV, both targeted for Q1 2017. The table therefore offers a more specific view of the Hong Kong construction pipeline, but it does not establish that the news report’s Hong Kong reference corresponded to only one of those entries.
Equinix presented Hong Kong as a fast-growing Asia-Pacific data-center market, with demand associated with cloud services, digital content, financial services and connectivity between mainland China and international markets. Its broader rationale was the density of carriers, network operators, mobile providers, internet service providers, cloud services and content companies. A separate Equinix announcement described HK5, scheduled for Q4 2017 with more than 48,000 square feet and 1,200 cabinets; it should not be substituted for the unnamed Hong Kong project in the 2016 report. Equinix’s Hong Kong expansion announcement and its separate HK5 announcement
Rank #3
- Sturdy:4u server rack is construct from cold rolled steel, with a weight capacity of 110lbs(50kg); Electrostatic powder coat prevents rust and corrosion,quality finish
- Direct use:Open and use, not having to assemble it.Network rack can be placed flat or mounted on the wall,also can be installed vertically under the table
- Design Features:maximum mounting depth of 14 in,cables can be fixed on the side panel;Open frame server rack achieves effortless inspection, replacement and assemble
- Installation:wall mount network rack is easy to install,with instructions or videos for reference;Equipped with multiple accessories, suitable for different needs
- Application:EIA/ECA-310-E Compliant;wall mounted 4u rack fits all 19" racks and cabinets to hold various IT, network, and AV equipment;wall mount rack available in 4U, 6U, and 8U to choose
What the expansion says about Equinix’s strategy
The projects favored established, high-demand markets and existing campuses. That approach can put new capacity close to customers and network ecosystems, while using campus infrastructure and interconnection density to support more than colocation alone. It also exposes a basic constraint: sought-after metros can be difficult places to secure land and power, and phased development cannot deliver the full planned capacity immediately.
Equinix was adding supply through a mix of new construction, phased campus expansions, acquisitions and leases. Its strategic case rested on strong utilization and returns on development capital, alongside customer demand for carrier-neutral colocation and direct interconnection. The company described Asia-Pacific growth at the time as faster than growth in Europe and the Americas. These are strategic themes and management characterizations, not proof that every project achieved the same utilization or return.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
What happened after the announcement
The clearest confirmed outcome in the cited material is SV10: Equinix announced that it opened the facility in 2017, with the initial phase’s more than 37,000 square feet and 930-cabinet capacity. By contrast, the Q1 and Q2 2017 dates for HK1, HK2 and NY5 in the annual report are target openings, not confirmation of completion. The company’s later expansion activity shows that these metros remained part of its development footprint, but the 2016 report should be read as a snapshot of planned projects—not as a current construction announcement or a single three-site build with a settled final cost.
A cabinet count also does not establish available power, supported rack density, cooling capability or customer-ready capacity. Those details require project-specific specifications rather than an inference from the announced cabinet totals.