Data Foundry announced the Houston 2 groundbreaking for April 10, 2014, at 660 Greens Parkway in North Houston’s Greens Crossing district. The project was planned as a 350,000-square-foot data center on an 18-acre site, with customer deployments targeted for the first quarter of 2015. Data Foundry later said the facility opened in June 2015 and expanded it with a 27,000-square-foot, 4-megawatt data hall completed in February 2020.
When did Data Foundry break ground on Houston 2?
Data Foundry announced the groundbreaking ceremony on April 8, 2014, for April 10 at 660 Greens Parkway. The company described Houston 2 as its second and largest Houston-area data center, while Houston 1 continued operating in the Galleria/West Loop area.
As an Amazon Associate I earn from qualifying purchases.
Where is Data Foundry Houston 2?
Houston 2 is at 660 Greens Parkway in the Greens Crossing district of North Houston. The original campus plan covered 18 acres.
What was the original Houston 2 plan?
- Planned building area: 350,000 square feet.
- Site: 18 acres in Greens Crossing.
- Target readiness: customer deployments in the first quarter of 2015.
Those figures come from Data Foundry’s 2014 project announcement and describe the proposed development at that date, not a later independently measured as-built area.
#1 Best Overall
- Save valuable floor space: 6U wall mount server cabinet Dimensions: 13.78" H x21.65" W x17.72" D.Maximum mounting depth is 14.2"
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access. Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punch-out panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
When did Houston 2 open?
Data Foundry announced on June 3, 2015, that Houston 2 was open for business. In that announcement, the operator listed a 350,000-square-foot facility with a stated capability of up to 60 megawatts, 60,000 square feet of dedicated office space, chilled-water cooling and carrier-neutral connectivity. It also described construction above the 500-year flood plain and a wind rating of 185 mph. These are operator-published specifications, not independently audited performance measurements.
How much power capacity does Houston 2 have?
Data Foundry’s 2015 opening announcement described Houston 2 as capable of 60 MW. That is the company’s stated capability for the original facility. It should not be read as 60 MW of currently occupied load or as a guarantee of available capacity for a prospective customer.
What happened after Houston 2 opened?
2019 expansion announcement
On September 24, 2019, Data Foundry announced an additional 27,000-square-foot data hall designed to add 4 MW of capacity.
The Tool Desk
Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Rank #2
- Save valuable floor space: 12U wall mount server cabinet Dimensions: 24.25" H x21.65" W x17.72" D. MAXIMUM MOUNTING DEPTH is 14.2".
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access; Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punchout panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
2020 expansion completion
On February 10, 2020, the company reported that the expansion was complete. Ronald Yokubaitis, Data Foundry’s co-CEO, said: “We couldn’t be happier to expand our capabilities to meet the needs of our clients as they grow and evolve.” The statement expresses the operator’s view of the project’s purpose.
Regulatory project record
A Texas Department of Licensing and Regulation record identifies Houston 2 POD 2 as a 27,079-square-foot interior data-center fit-out. The record lists the project as closed and gives an estimated completion date of June 1, 2020. The 27,000-square-foot company figure and the regulator’s 27,079-square-foot scope are separate reported measurements; they may reflect different definitions or estimates and should not be silently combined.
Houston data-center market context
“Booming Houston market” is framing for the project, not a conclusion established by the construction announcements alone. Data Foundry said the development was intended to meet customer demand and support growth, which is the company’s stated rationale.
Rank #3
- Sturdy:4u server rack is construct from cold rolled steel, with a weight capacity of 110lbs(50kg); Electrostatic powder coat prevents rust and corrosion,quality finish
- Direct use:Open and use, not having to assemble it.Network rack can be placed flat or mounted on the wall,also can be installed vertically under the table
- Design Features:maximum mounting depth of 14 in,cables can be fixed on the side panel;Open frame server rack achieves effortless inspection, replacement and assemble
- Installation:wall mount network rack is easy to install,with instructions or videos for reference;Equipped with multiple accessories, suitable for different needs
- Application:EIA/ECA-310-E Compliant;wall mounted 4u rack fits all 19" racks and cabinets to hold various IT, network, and AV equipment;wall mount rack available in 4U, 6U, and 8U to choose
For a current comparison point, CBRE’s H1 2025 Houston profile reported that a recent delivery by one operator increased market vacancy to 19.7%. The same profile said 15 MW of additional capacity was scheduled through year-end 2026, while oil-and-gas occupier demand continued. It also noted legacy space returning to the market and two enterprise data-center acquisitions for large-scale colocation development.
Those CBRE figures describe the H1 2025 snapshot. They cannot be transplanted onto conditions in 2014, and scheduled 2026 capacity is not the same as capacity already delivered.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.How to read the facility figures
| Figure | What it describes | Source context |
|---|---|---|
| 350,000 sq. ft. | Original Houston 2 facility size | Data Foundry opening announcement, 2015 |
| 60 MW | Stated capability for the original facility | Data Foundry, 2015; operator specification |
| 18 acres | Original campus parcel | Data Foundry groundbreaking announcement, 2014 |
| 27,000 sq. ft. | Expansion data hall announced and completed by the company | Data Foundry, 2019–2020 |
| 4 MW | Power capacity associated with the announced expansion | Data Foundry, 2019–2020 |
| 27,079 sq. ft. | POD 2 interior fit-out scope | Texas Department of Licensing and Regulation record |
Ownership and current-service caveat
Data Foundry’s history page records Houston 2’s 2015 grand opening and says Switch acquired Data Foundry in 2021. The current company site still presents Houston 2 under the Data Foundry name. The sources available here do not establish every subsequent ownership or operating change, so buyers should confirm today’s contracting entity, available space, power, connectivity and service terms directly with the provider.
What this means for infrastructure buyers
- Use the 2014 and 2015 announcements to understand the original campus plan and operator-stated design.
- Use the 2019–2020 records to distinguish the later POD 2 expansion from the original 350,000-square-foot facility.
- Treat 60 MW and the other engineering characteristics as published specifications, not an independent availability assessment.
- Separate a market snapshot’s vacancy and scheduled supply from a facility’s commissioned or sellable capacity.
- For a current colocation decision, request written confirmation of power availability, delivery dates, flood and wind protections, network carriers, security controls, pricing and contractual counterparty.
The Bottom Line
Houston 2 moved from a planned April 2014 groundbreaking to a June 2015 opening, then gained a separately reported 27,000-square-foot, 4-MW data hall completed in 2020. Its 60-MW capability and resilience features are Data Foundry specifications, while Houston’s later market indicators show both continuing demand and meaningful available or returning supply.