One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware matchGoogle’s proposed $600 million data center in Becker, Minnesota, was not built. Google affiliate Honeycrisp Power missed a deadline to tell Xcel Energy to proceed, and Xcel terminated the project’s electric service agreements on December 8, 2022. Google did not publicly explain why it pulled out. The $600 million and job figures were estimates for a proposed project—not money spent or jobs created.
What Google proposed for Becker
The proposal was for a data center near Xcel Energy’s Sherco power plant in Becker, Sherburne County. In a 2019 filing supporting Xcel’s request for electric service agreements, Google LLC described the plan as conditional: “If the project moves forward, the project would generate at least $600 million in initial capital investment.” That was Google’s projection, not a Minnesota Public Utilities Commission finding or a record of completed investment. Minnesota PUC filing
Sherburne County project materials described a facility of approximately 375,000 square feet on roughly 315 acres, with an estimated $600 million investment: $300 million for construction and $300 million for equipment purchases. Those figures also described the proposal, not a facility that was built. Sherburne County project materials
What happened to the project
- 2019: Google’s filing backed Xcel’s request for electric service agreements for the proposed Becker data center.
- By the project deadline: Honeycrisp Power did not give Xcel the required notice to proceed, according to the Star Tribune.
- December 8, 2022: Xcel terminated the electric service agreements.
- December 21, 2022: The Star Tribune reported that Google had pulled out. Construction never began. Star Tribune report
The word “pauses” in the December 21 headline can suggest the project was simply waiting to restart. The reported record is more specific: the agreements ended after the notice-to-proceed deadline passed, and the proposed Becker facility was not constructed.
Do these 3 things before closing this tab:
1Fix the driver behind crashes, sound loss and screen glitches2Clear out junk files and repair common Windows errors3Scan for outdated or missing drivers - takes under a minute#1 Best Overall
- Save valuable floor space: 6U wall mount server cabinet Dimensions: 13.78" H x21.65" W x17.72" D.Maximum mounting depth is 14.2"
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access. Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punch-out panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
Was the $600 million investment made?
No. The $600 million was a proposed investment estimate. Since construction never began, it should not be described as money invested in a completed Becker data center. The same distinction applies to the projected jobs:
| Figure | What it described |
|---|---|
| At least $600 million | Google’s projected initial capital investment if the project moved forward, stated in its 2019 PUC filing. Minnesota PUC filing |
| Nearly 2,000 jobs | Construction jobs projected in Google’s 2019 filing, not jobs shown to have been created. Minnesota PUC filing |
| At least 50 jobs | Permanent technology-sector positions projected if the facility was built, not realized employment. Minnesota PUC filing |
Why did Google pull out?
The public reporting cited here does not establish Google’s internal commercial or technical reason. The documented step was Honeycrisp Power’s failure to provide the notice to proceed by the deadline; Xcel then terminated the service agreements. The Star Tribune reported that Google gave no reason for pulling out.
Rank #2
- Save valuable floor space: 12U wall mount server cabinet Dimensions: 24.25" H x21.65" W x17.72" D. MAXIMUM MOUNTING DEPTH is 14.2".
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access; Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punchout panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
Google’s statement, quoted by the Star Tribune on December 21, 2022, was: “While this project isn’t progressing right now, that doesn’t rule out engagement on projects in the future.” That statement left open the possibility of other or later projects; it did not say the Becker facility would resume. Star Tribune report quoting Google
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.What about the $20.5 million for Becker infrastructure?
The Star Tribune reported that Minnesota appropriated $20.5 million for Becker industrial-park infrastructure improvements, mainly water and sewer extensions, with construction occurring primarily in 2022 and 2023. The report does not establish how much of the appropriation was ultimately spent, whether all planned work was completed, or how each improvement was used. It therefore does not support saying that the entire sum was spent on Google—or that all of the work was left stranded. Star Tribune report
Rank #3
- Sturdy:4u server rack is construct from cold rolled steel, with a weight capacity of 110lbs(50kg); Electrostatic powder coat prevents rust and corrosion,quality finish
- Direct use:Open and use, not having to assemble it.Network rack can be placed flat or mounted on the wall,also can be installed vertically under the table
- Design Features:maximum mounting depth of 14 in,cables can be fixed on the side panel;Open frame server rack achieves effortless inspection, replacement and assemble
- Installation:wall mount network rack is easy to install,with instructions or videos for reference;Equipped with multiple accessories, suitable for different needs
- Application:EIA/ECA-310-E Compliant;wall mounted 4u rack fits all 19" racks and cabinets to hold various IT, network, and AV equipment;wall mount rack available in 4U, 6U, and 8U to choose
Is Google planning other data centers in Minnesota?
Minnesota PUC information lists separate proposals involving Google affiliates in Hermantown and Pine Island. They are distinct projects, not a revival of the Becker proposal. The PUC describes its data-center role as including review of electric service agreements, public notice and comment, reliable service, and protecting ratepayers from infrastructure costs shifted onto them. Minnesota PUC data-center information Minnesota PUC role and process
Quick Recap