Hardware FixRecommendedDevice not working? Your driver may be the problemCheck updates for common hardware issues.Fix DriversOctober DealsAmazon USOctober deal check: compare before you payAmazon US: current deals, useful picks and tech finds.Check DealsPC HealthRecommendedCrashes, freezes, slowdowns? Check your PC nowSpot repairable issues before they interrupt work.Check PC×
Skip to content
The Finance Base
The Money Desk · Blog
Re:

New Data Center Developments: October 2025 — Projects, Power and Financing

October 2025 data-center news ranged from confirmed construction starts to financing deals and proposals, with AI demand and power access shaping the buildout.
From TheFinanceBase Team9 min to read
Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

October 2025 brought a wave of data-center announcements driven by artificial-intelligence demand, but the headlines describe very different stages of development. Some projects broke ground; others secured financing, acquired land, or remained proposals. The clearest examples of physical progress were Related Digital’s Cheyenne campus, Data4’s Hanau construction, and new facilities advancing in Kenya and elsewhere. Meanwhile, the scale of planned AI campuses made power access, financing and local impacts central parts of the story.

This roundup covers projects announced, reported or advanced during October 2025, even where the original commitment may have come earlier. Planned megawatts are not operating capacity, and investment figures may represent a multi-year commitment, financing transaction or projected buildout rather than money already spent.

October’s most consequential developments

These projects illustrate why an announcement, a construction start and a financing deal should not be treated as equivalent milestones.

Development October status What was announced or underway
Related Digital, Cheyenne, Wyoming Groundbreaking A first phase described as a $1.2 billion project within a campus planned for up to 302 MW of critical IT capacity. CoreWeave is the anchor tenant for 88 MW under a long-term lease.
Stargate, United States Planned expansion OpenAI said five additional sites, alongside existing projects, brought planned capacity to nearly 7 GW and more than $400 billion in planned investment over three years. These are company projections, not operating capacity.
Meta and Blue Owl, Hyperion Financing and development joint venture Blue Owl funds contributed approximately $7 billion in cash to the joint venture; Meta received a one-time distribution of approximately $3 billion and contributed land and construction-in-progress assets.
Data4, Hanau, Germany Construction underway A campus planned for 180 MW, with investment of up to €2 billion, on a former military-base site.
Argonne AI systems Announced; construction beginning for Equinox The U.S. Department of Energy described two systems with 10,000 and 100,000 NVIDIA Blackwell GPUs. This is public-sector supercomputing infrastructure, not a conventional commercial colocation campus.

Sources: Related Digital, OpenAI, Meta and Blue Owl announcement, Digital Core REIT operational update, and the U.S. Department of Energy.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
#1 Best Overall
Tecmojo 6U Wall Mount Server Cabinet IT Network Rack Enclosure Lockable Door and Side Panels Black, Cooling Fan, Standard Glass Door, 450mm Depth, for 19” IT Equipment, A/V Devices
  • Save valuable floor space: 6U wall mount server cabinet Dimensions: 13.78" H x21.65" W x17.72" D.Maximum mounting depth is 14.2"
  • Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access. Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
  • Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punch-out panels for easy cable access
  • Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
  • PCI & HIPPA and EIA/ECA-310-E compliant

North America: AI campuses and enabling infrastructure

Stargate’s U.S. site expansion

OpenAI announced five additional U.S. sites with Oracle and SoftBank. Named or described locations included Shackelford County and Milam County in Texas, Doña Ana County in New Mexico, Lordstown, Ohio, and a Midwest site later identified as Wisconsin. OpenAI said the three Oracle-related sites could provide more than 5.5 GW; Ohio and Texas projects developed through SoftBank partnerships could scale to 1.5 GW over 18 months. Those figures are planned capacity, not commissioned IT load. A potential 600-MW expansion near Abilene was also described. OpenAI’s broader stated goal was $500 billion and 10 GW by the end of 2025.

The distinction matters to investors and communities: a large capacity target signals intent and potential demand for land, power and construction, but it does not show that utilities have energized the sites or that customers can use the capacity.

Cheyenne: a construction milestone with an AI tenant

Related Digital broke ground on a 115-acre Cheyenne campus. Its first building is described as 184,000 square feet on 36 acres, with completion expected in late 2026. The developer says the design uses air-cooled chillers to minimize water consumption, with water use primarily for domestic needs. That is a project-specific design claim, not a general measure of water use at AI facilities. Related also projected more than $250 million in city and state tax revenue over the first 15 years, more than 700 construction jobs and 40 permanent jobs; these are developer projections.

Other U.S. projects and transactions

  • New Mexico: Doña Ana County approved a $165 million industrial-revenue-bond package and tax incentives supporting four data centers and associated energy facilities by BorderPlex Digital Assets and Stack Infrastructure.
  • Kansas City: A proposed Berkley Riverfront campus was described as a $100 billion development across 379 acres, with six hyperscale data centers totaling 1.8 million square feet. It is a proposal, not operating capacity or confirmed spending.
  • Naval Air Station Lemoore, California: Ameresco, the U.S. Navy and CyrusOne planned a 100-MW AI-optimized facility with on-site energy-generation infrastructure.
  • Gallatin, Tennessee: Meta was reported to be using rapid-deployment, weatherproof structures at its campus. The approach points to attempts to shorten delivery schedules; it does not mean the entire permanent campus is a tent.
  • Portfolio acquisition: Centersquare announced plans to acquire 10 data centers across the United States and Canada for approximately $1 billion, which would expand its portfolio to 80 facilities. This is an ownership transaction, not 10 newly built centers.
  • Specialized capacity: HydraVault planned a Tier 3-compatible Chicago facility for AI, machine learning and low-latency financial trading, with customer buildout estimated for 2026. Duos Edge AI deployed its fifth data center in Dumas, Texas, with the local independent school district. Oxford Quantum Circuits installed a quantum computer at Digital Realty’s Manhattan facility, described in the roundup as New York City’s first.

Grid and power supply

Hitachi Energy planned to invest $1 billion in grid-production capacity in response to data-center construction. Babcock & Wilcox and Denham Capital announced a partnership involving power-generation technologies, including converting coal plants to natural gas. These are enabling energy developments, not data-center capacity. They also underscore a practical constraint: a site’s announced megawatts do not establish that it has transmission access, an interconnection agreement or a reliable power supply.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Europe: construction, rented compute and policy choices

United Kingdom and Norway

The October roundup reported a $15 billion Nvidia–OpenAI initiative involving about 300,000 GPUs and data-center development through Nscale and CoreWeave. It also reported that Nscale raised $1.1 billion and was selected to develop OpenAI’s first Stargate site in the United Kingdom. These are secondary-source claims in the available coverage; they should not be read as proof that the stated GPUs were installed or that the full investment had been spent.

Rank #2
Tecmojo 12U Wall Mount Server Cabinet IT Network Rack Enclosure Lockable Door and Side Panels Black,Cooling Fan,Glass Door,17.7inch Depth,for 19” IT Equipment,A/V Devices
  • Save valuable floor space: 12U wall mount server cabinet Dimensions: 24.25" H x21.65" W x17.72" D. MAXIMUM MOUNTING DEPTH is 14.2".
  • Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access; Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
  • Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punchout panels for easy cable access
  • Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
  • PCI & HIPPA and EIA/ECA-310-E compliant

In Norway, Microsoft reportedly agreed to rent AI-compute capacity in a $6 billion arrangement, with Aker ASA and Nscale identified as providers. That describes a capacity agreement, not necessarily a Microsoft-owned data-center construction project.

Germany, the Netherlands and London

  • Hanau, Germany: Data4 began construction on a planned 180-MW campus at a former military base. The company bought the roughly 25-acre site in 2023 and planned investment of up to €2 billion.
  • Germany and the Netherlands: Oracle planned to invest $3 billion over five years in AI and cloud infrastructure: $2 billion focused on Germany’s Frankfurt cloud region and $1 billion in the Netherlands.
  • Frankfurt: IONOS launched an 86,111-square-foot facility designed for AI, government, financial-services and other data-intensive workloads. The operational update reported a PUE of 1.23 at full load and renewable-energy operation.
  • London: Vantage launched a second London campus facility of 194,000 square feet and 20 MW of IT capacity, as part of a planned three-campus buildout.

Gibraltar and Ireland

Pelagos Data Centres planned a 250-MW facility near the Port of Gibraltar, in five phases. The first phase was scheduled for late 2027, and the proposal called for operating independently of Gibraltar’s existing power grid. Ireland, meanwhile, was considering policy changes that could allow data centers to use fossil-fuel generation or private grid connections amid energy constraints. The policy remained under review, not final.

Latin America: a large Mexican proposal and a land-rights dispute

Mexico City

CloudHQ was reported to be planning six data centers in Mexico City, with a proposed $4.8 billion investment and a 900-MW private substation expected to open in 2027. The scale makes the power arrangement especially consequential, but the reported plan should not be mistaken for a completed build or a verified construction schedule.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Guatemala and Brazil

  • Guatemala: Kio Data Centers planned a second facility, initially configured with two rooms of 500 kW each, with potential expansion to four rooms totaling 2 MW of IT load.
  • Brazil: A legal challenge was reported against TikTok’s planned $10 billion data-center project. The Anacé Indigenous community alleged that authorities had not provided proper consultation and disputed land rights. The challenge illustrates how consultation, land claims and environmental review can materially affect a project’s path.

Asia-Pacific: regional capacity and early-stage discussions

Japan and China

  • Osaka, Japan: EdgeConneX acquired a second data-center site in the Greater Osaka/Yawata area, with the completed site expected to provide 150 MW. Acquisition is not the same as completed capacity.
  • Yokohama, Japan: JERA signed a memorandum of understanding to explore a data center on thermal-power-station grounds using low-carbon and decarbonized electricity. An MOU does not establish a final investment decision or construction start.
  • China: A consortium led by Shenzhen Dongyangguang Industry reportedly completed a $4 billion acquisition of Bain Capital’s data-center assets in China. This is a portfolio ownership change, not new-build capacity.

India, Australia and New Zealand

  • India: OpenAI reportedly began discussions with Sify Technologies, Yotta Data Services, E2E Networks and CtrlS Datacenters about potential Stargate infrastructure. The discussions were exploratory, not a confirmed construction project.
  • Sydney, Australia: GreenSquareDC advanced a campus planned for 110 MW. The company reportedly secured approval for an initial 15 MW of AI-enabled capacity and appointed a general contractor; first-phase completion was expected in the third quarter of 2026.
  • New Zealand: Amazon launched cloud services in the country and planned to invest more than $4.4 billion in data centers across the South Pacific nation. The investment plan is not equivalent to $4.4 billion of newly commissioned facilities.

Middle East and Africa: investment and new construction

  • Malaysia: Abu Dhabi Investment Authority invested $1.6 billion in Vantage Data Centers, enabling Vantage to acquire a 300-MW facility. This is a financing and ownership development with implications for regional capacity.
  • Egypt: Helios Investment Partners received preliminary approval from Telecom Egypt to acquire a majority stake in a new subsidiary holding the operator’s Regional Data Hub assets in Cairo. The approval was preliminary, so the transaction should not be described as completed.
  • Kenya: Airtel began construction on a 44-MW data center in Tatu City, described as supporting high-density GPU-ready racks, redundant fiber paths and enhanced security.
  • Angola: Raxio Group was building a facility described as Angola’s first Tier 3 data center, designed for up to 800 racks and 7 MW of IT power. The available description does not establish whether the facility has Tier 3 certification.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

What the announcements reveal about data-center development

AI is changing the scale and design brief

GPU-heavy workloads raise requirements for power density, cooling, network connectivity and rapid delivery. The Cheyenne CoreWeave lease, planned Stargate capacity, reported UK GPU initiative and Argonne systems all point to AI as a major driver. But a GPU count or planned campus size alone says little about when usable capacity will be available.

Power is part of the project, not a footnote

Private substations, on-site generation, proposed grid-independent operation and grid-equipment investment recur across the announcements. For operators, power access can determine site viability and delivery timing. For communities and utilities, the implications include transmission planning, competing demand and potential changes to generation. A claimed renewable or low-carbon supply also needs context: a direct supply arrangement, a power-purchase agreement and reliance on a regional grid mix are not interchangeable.

Rank #3
Tecmojo 4U Wall Mount Rack,4U Rack 14 inch Depth,19" Network Rack for Shallow Server and IT Equipment, Network Switches,Patch Panel Bracket,110lbs(50kg) Weight Capacity,Black
  • Sturdy:4u server rack is construct from cold rolled steel, with a weight capacity of 110lbs(50kg); Electrostatic powder coat prevents rust and corrosion,quality finish
  • Direct use:Open and use, not having to assemble it.Network rack can be placed flat or mounted on the wall,also can be installed vertically under the table
  • Design Features:maximum mounting depth of 14 in,cables can be fixed on the side panel;Open frame server rack achieves effortless inspection, replacement and assemble
  • Installation:wall mount network rack is easy to install,with instructions or videos for reference;Equipped with multiple accessories, suitable for different needs
  • Application:EIA/ECA-310-E Compliant;wall mounted 4u rack fits all 19" racks and cabinets to hold various IT, network, and AV equipment;wall mount rack available in 4U, 6U, and 8U to choose

Financing is diversifying

Meta’s Hyperion joint venture shows how a hyperscaler can combine its land and construction assets with institutional capital. Other announcements involved acquisitions, investment commitments and long-term capacity arrangements. Those structures can distribute capital needs and development risk, but a financing announcement does not prove that a facility is built, energized or fully leased.

Land, water and community consent can shape timelines

Repurposing a former military site in Hanau and using air-cooled chillers in Cheyenne show how location and design choices are presented as part of project planning. They do not settle broader questions about water, land use or local impact. The Brazil challenge and Ireland’s energy-policy debate make clear that permitting, consultation, fuel choices and grid rules can influence whether a proposal proceeds as announced.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

How to read a data-center announcement

Capacity and investment figures are not directly comparable unless their definitions and project status are clear.

  • Capacity: MW may refer to critical IT load, utility power, total campus power, an initial phase or ultimate buildout. It may also describe generation capacity rather than computing load.
  • Investment: A figure may be a multi-year company plan, projected campus value, financing amount, property transaction or economic-impact estimate. It is not necessarily capital already deployed.
  • Status: Groundbreaking or active construction is stronger evidence of physical progress than site acquisition or an announcement. Financing, an MOU and exploratory talks each signal different levels of commitment.
  • Operations: A facility launch does not establish full occupancy or full buildout. Check whether it is open to customers, partially energized or serving workloads.
  • Power and cooling: Look for interconnection, substations, generation, storage and cooling details. General claims about renewable energy or low water use should be tied to the specific project and design.

What to watch after October 2025

The useful follow-up signals are not simply revised headline totals. They are whether projects secure permits and financing, connect to the grid, begin construction, obtain tenants, receive equipment and energize the promised capacity. For contested or exploratory projects, legal decisions, community consultation and policy changes can be just as consequential as a developer’s schedule.

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.

Leave a Reply

Your email address will not be published. Required fields are marked *

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

More post from the Money Desk

  1. The Money DeskBlogTheFinanceBase09 OCT 267 minMortgage Escrow FAQs: Taxes, Insurance, Shortages, and Refunds
  2. The Money DeskBlogTheFinanceBase09 OCT 265 minHow Mortgage Escrow Accounts Work and What Homeowners Pay For
  3. The Money DeskBlogTheFinanceBase09 OCT 265 minHow to Read a Stock Chart, Volume and Market-Cap Data
Recommended PC Tool
Recommended PC Tool
Windows Errors? Fix Them Before They SpreadFree repair scan
Outdated Drivers Are Slowing You DownFree scan - exact matches

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.