Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Kevin O’Leary’s Wonder Valley is a real Alberta development proposal, not an operating or under-construction data centre. O’Leary Digital and O’Leary Ventures plan an AI data-centre industrial park in the Greenview Industrial Gateway near Grande Prairie, with on-site natural-gas generation and geothermal power described in the original announcement. Alberta’s Major Projects database lists the first phase as “Proposed,” with 1.4 gigawatts of planned off-grid power and an estimated cost of C$12 billion. The company’s longer-term vision is much larger: a 7.5-GW Alberta campus and more than C$70 billion in potential lifetime investment.
What is Wonder Valley?
Wonder Valley is the proposed Wonder Valley AI Data Centre Industrial Park in the Greenview Industrial Gateway near Grande Prairie, northwestern Alberta. Kevin O’Leary is chairman of O’Leary Digital/O’Leary Ventures, which announced the partnership with the Municipal District of Greenview on December 9, 2024. The announcement described a campus for hyperscale cloud and artificial-intelligence computing customers, supplied by dedicated power infrastructure rather than relying entirely on Alberta’s electricity grid.
The company’s website describes an Alberta campus of about 13,000 acres and 7.5 GW of planned capacity (O’Leary Digital). Those are master-plan figures, not evidence that the land, buildings, generators or tenants have been delivered.
Is it actually natural-gas-powered?
The proposal is built around on-site natural-gas generation. The original announcement also included geothermal resources, while the current company material emphasizes integrated generation and a carbon-capture-ready design (announcement; company site).
Do these 3 things before closing this tab:
1Clear out junk files and repair common Windows errors2Scan for outdated or missing drivers - takes under a minute3Repair Windows errors before they cause bigger problems#1 Best Overall
- Save valuable floor space: 6U wall mount server cabinet Dimensions: 13.78" H x21.65" W x17.72" D.Maximum mounting depth is 14.2"
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access. Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punch-out panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
It is too early to say the finished campus will run only on gas. No final public engineering plan establishes the generating units, fuel contracts, backup systems, grid connection, export capability or islanding arrangements. “Off-grid” in the Alberta project listing should be read as dedicated on-site or behind-the-meter generation, not as freedom from provincial regulation or proof of total physical isolation.
How large is the project?
The headline numbers refer to different scopes and stages:
| Figure | What it describes |
|---|---|
| 1.4 GW | Alberta government description of Phase 1’s planned off-grid power system |
| 7.5 GW | O’Leary Digital’s planned Alberta campus capacity |
| 15 GW | Combined Alberta-and-Utah campus plan described by the company |
| C$12 billion | Estimated Phase 1 cost in Alberta’s Major Projects database |
| More than C$70 billion | Proponent’s projected lifetime investment for the Alberta development, including power, data centres and related infrastructure |
Alberta’s official listing currently labels Wonder Valley “Proposed” (Major Projects database). The 7.5-GW and C$70-billion figures are long-range projections, not current spending or operating capacity.
Why the proponents chose Alberta
O’Leary Digital and Greenview point to several advantages:
Rank #2
- Universal 19” Rack Mount Compatibility – Perfect for pro audio, video, IT, and network gear. Compatible with mixers, routers, patch panels, servers, power amps, and more.
- Heavy-Duty Load Capacity – Built to support up to 550 lbs. Ideal for studio gear, DJ setups, server equipment, and AV components that demand serious stability.
- Robust Steel Frame & Design – Made with 1.5mm thick steel and weighs 36 lbs for maximum durability, reduced vibration, and long-term reliability in any setting.
- Mobile & Secure – Preinstalled with 3” industrial-grade caster wheels (lockable), making it easy to move and position your rack exactly where you need it.
- All-In-One Setup Kit Included – Comes with 34 rack screws (5mm & 6mm), a 1U blank spacer, and an assembly tool—ready for fast installation out of the box.
- Regional natural-gas resources and existing oil-and-gas infrastructure.
- Large industrial land holdings in the Greenview Industrial Gateway.
- Fibre connectivity and transportation infrastructure.
- A cool climate that may reduce cooling requirements.
- The ability to build dedicated generation behind the data centre instead of waiting for a large new grid connection.
- Alberta policies intended to attract data centres and permit private power supplies.
These are site-selection arguments, not independently demonstrated project outcomes. Access to land, gas or fibre does not establish that contracts, interconnections and construction financing are complete.
Current status: proposed, with permitting said to be underway
O’Leary Digital said on February 17, 2026 that permitting was underway for the Alberta project and that it had begun engagement with Indigenous communities whose traditional lands include the gateway (company announcement). That statement does not establish a final investment decision or a construction start.
| Milestone | Verified position |
|---|---|
| Public announcement | December 9, 2024 |
| Alberta location | Greenview Industrial Gateway near Grande Prairie |
| Public status | Proposed |
| Permitting | Company said it was underway in February 2026 |
| Confirmed construction start | Not established in the cited authoritative sources |
| Confirmed hyperscale tenant | Not established in the cited authoritative sources |
| Operating data centre | No |
Greenview’s spring 2026 newsletter says some project information remains confidential (Greenview update).
The water licence—and what it does not prove
On April 7, 2025, Alberta issued the Municipal District of Greenview No. 16 a Water Act licence authorizing diversion from the Smoky River for commercial and industrial purposes in the Greenview Industrial Gateway. The licence allows up to 6 million cubic metres per year at a maximum rate of 0.56 cubic metres per second (Environmental Appeals Board decision).
Rank #3
- ADJUSTABLE DEPTH: 4- Post 22U 19" server rack enclosure with 4 vertical rails and adjustable mounting depth 5.7" to 33.0" (14,4cm to 83,8cm); IT rack is compatible with various servers / switches / data / video / AV and other IT networking equipment
- EASY SHIPPING AND ASSEMBLY: Enclosed 22U data rack cabinet ships compact flat-packed to avoid damage and facilitate installation; Include wheels & levelling feet to offer more stability; Home server rack cabinet is only 46.6in (118,3cm) in height
- DESIGN AND VENTILATION: Half height server rack cabinet has lockable and removable door and side panels with vented top allowing airflow; 4 Post 19" rack with 1764lb (800kg) weight capacity (stationary); Computer cabinet rack is EIA/ECA-310-E Compliant
- HARDWARE INCLUDED: Rolling home network rack includes rack mounting and equipment mounting hardware, such as 20 M6 cage nuts / screws, PVC cup washers; Front/rear doors and side panels Keys, 2x allen keys; Rack assembly hardware; Casters and leveling feet
- THE IT PRO'S CHOICE: Designed and built for IT Professionals, this 22U IT Server Cabinet is backed for life, including free lifetime 24/5 multi-lingual technical assistance
That authorization is not the data centre’s measured consumption and is not approval of the complete Wonder Valley campus. The actual water balance would depend on how much is withdrawn and consumed or evaporated for power generation, cooling, construction and other industrial uses, plus how wastewater and thermal discharge are managed.
Indigenous consultation and the legal dispute
Sturgeon Lake Cree Nation challenged the water-licensing process. In reasons dated April 17, 2026, the Environmental Appeals Board dismissed that particular appeal because it found the Nation was not directly affected for the purpose of standing. The Board said it therefore did not need to decide the constitutional jurisdiction and duty-to-consult questions in that proceeding (decision).
That ruling did not approve the full data centre, erase other consultation duties or resolve any separate judicial-review proceedings. Later court developments should be checked against the Alberta Court of King’s Bench record before being described as final.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Environmental approvals and climate trade-offs
There is no single approval called an “AI data-centre approval.” The project may require separate authorizations for natural-gas generation, air emissions, water diversion, cooling and wastewater, land disturbance, roads, pipelines or transmission, wildlife and wetlands, and potential carbon-management infrastructure. Alberta’s framework says environmental assessment depends on factors such as scale, complexity, technology, resource use and potential for significant adverse effects. Activities affecting land, water and air can also require approvals under the Environmental Protection and Enhancement Act (assessment process; approvals framework; EPEA approvals; authorization tools).
Quick wins for a faster PC:
Clear out junk files and repair common Windows errorsFree Scan →Fix the driver behind crashes, sound loss and screen glitchesFind Drivers →Rank #4
- DURABLE BUILD: Constructed from high-quality Cold Rolled Steel, the NavePoint Consumer Series 12U network cabinet boasts a sturdy, welded frame. Fitting EIA standard 19” networking equipment, this server cabinet confidently supports up to 110 lbs, providing a resilient base for your vital IT gear and equipment
- CONVENIENT DESIGN: This 12U cabinet features a reinforced, heat-treated, tempered glass front door with a security lock. Perfect for applications requiring both security and accessibility, its compact design of 17.72"L x 21.65"W x 24.42"H offers a practical solution for space-constrained settings.
- EASY & CUSTOMIZABLE EQUIPMENT SET UP - The 12U IT cabinet, with removable side panels and security locks, offers customization at its finest. Whether it's for an efficient device or cable management, this data cabinet ensures secure, adaptable configurations that suit your networking server requirements
- ENHANCED VENTILATION & SECURITY - Built-in fans and flow-through ventilation work to prevent overheating, ensuring optimal operation of your equipment. The reinforced, lockable tempered glass front door not only boosts security but also facilitates easy monitoring of installed equipment.
- SAFETY & COMPLIANCE - All NavePoint products are built to industry standards.
Natural-gas generation could provide firm electricity without a major initial grid connection, but it would also raise questions about carbon dioxide, upstream methane, nitrogen oxides, noise, waste heat, water use and land fragmentation. “Carbon-capture-ready” means equipment could be accommodated; it does not establish that capture will be financed, permitted, installed or operated.
What must happen before the proposal is credible?
- A final investment decision and binding financing.
- Named cloud or AI customers with capacity commitments.
- Executed land agreements and final engineering for generation, cooling and data halls.
- Gas-supply, pipeline and equipment contracts.
- Air-emissions, water, wastewater, land-use and construction approvals.
- A funded schedule showing procurement, site work and commissioning.
The principal risks are unusually high capital requirements, tenant demand, turbine and electrical-equipment lead times, gas-price exposure, water and consultation disputes, and the possibility that AI-computing economics change before a multistage buildout is complete.
A separate Alberta project offers a useful scale comparison
Bitdeer broke ground near Fox Creek in June 2026 on a separate facility pairing a stated 101-MW natural-gas power plant with approximately 100 MW of computing capacity, targeting energization in the second quarter of 2027 (Bitdeer release; project page). Its construction milestone demonstrates a smaller behind-the-meter model; it is not evidence that Wonder Valley has reached the same stage.