Bell Canada and the Government of Saskatchewan announced a planned 300-megawatt AI data centre in the Rural Municipality of Sherwood, just outside Regina, on March 16, 2026. The facility is part of Bell’s AI Fabric network. It is under development—not an operating data centre—and Bell says the first data halls are expected to come online in the first half of 2027.
Bell estimates that the physical facility will require approximately $1.7 billion in capital spending. That figure excludes the AI compute hardware that tenants Cerebras and CoreWeave are expected to supply and fund separately.
What Bell announced
The announcement covers a partnership between Bell and the Government of Saskatchewan to develop a high-density AI data centre near Regina. Bell describes the planned site as the largest purpose-built AI data-centre development in Canada once complete.
The project is designed for AI training and inference—large-scale activities such as developing models and running them for users—rather than being limited to conventional consumer cloud storage. Bell says the centre will form part of its national Bell AI Fabric network.
#1 Best Overall
- 【Powerful Load-bearing】12U Network Rack Open Frame is constructed from durable cold rolled steel; Rack shelf supports enhance stability, wall-mounted capacity of 130lbs, the ground-mounted up to 260lbs
- 【Considerate Designs】Open-frame layout, including a top panel adding space, anti-slip shelf stops fixing devices and compatible racks for stack and expansion to meet requirements of home server rack
- 【Complete Accessories】A 12U open frame server rack, two ventilated shelves, four shelf stops, four velcro straps and a set of equipment mounting screws
- 【Versatile Application】Ideal for space-efficient multi-device setups in warehouses, retail, classrooms, offices and more; Excellent choices as AV Rack/IT Rack
- 【Effortless Setup】 Network Rack includes hardware, a comprehensive manual, mounting hole drilling template and an online assembly video to simplify setup
Where is the facility?
The site is in the Rural Municipality of Sherwood, immediately outside the City of Regina. Calling it a Regina data centre is understandable for general readers, but it is not technically located within Regina.
Bell’s project presentation says the Bell-owned property is adjacent to an existing SaskPower substation. The site is described as approximately 15 minutes from Regina International Airport and about six minutes from the University of Regina and Saskatchewan Polytechnic. Bell also plans to connect the facility to its national fibre network, with SaskTel involved as a connectivity and go-to-market partner.
Those features are commercially relevant: a large power connection, fibre access and proximity to research and technical institutions can help attract enterprise customers, researchers and AI developers. They do not, however, guarantee that the site will be open to every customer or that public cloud pricing will be available.
Crashes, No Sound, or Screen Glitches?
Random freezes, missing sound and display glitches usually trace back to one bad driver. Find and replace yours safely.Free scan · under a minutePC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11What does 300MW mean?
The 300MW figure primarily describes the facility’s planned electrical power capacity. It does not mean 300MW of computing power, a specific number of servers or a defined amount of storage.
Actual electricity use will depend on how quickly the site is built, how much capacity is commissioned, tenant utilization, cooling requirements and other operational factors. A facility planned for 300MW does not necessarily draw 300MW continuously from its first day of operation.
Bell’s materials indicate a staged development. Two data halls are planned for the first half of 2027, with two more expected in the latter half of the year. Future expansion parcels have also been identified, but that does not mean additional data centres have been approved, financed or scheduled.
Rank #2
- Space Saving: Maximum depth: 14.8". Use the wall mount network cabinet to maximize available space for retail locations, classrooms, back offices, network cabinets, and other locations where space is limited.
- Fast Heat Dissipation: The server cabinet is designed with vents to optimize airflow and avoid critical IT equipment overheating. Heat sink holes in the top, bottom, and rear panels are more conducive to heat dissipation.
- Sturdy Construction: Robust welded frame construction for durability and long service life. With 100 lbs wall-mounted load capacity and 200 lbs ground-mounted load capacity, you can place multiple devices in the server rack cabinet as needed.
- High Security: The locked glass door ensures the security of data and equipment. Wall mount rack enclosure server cabinet is ideal for use in public places such as offices, effectively protecting the security of your devices.
- Hassle-free Installation: Fully adjustable square-hole mounting rails of the wall mount server cabinet facilitate device installation. Wiring holes on the top, bottom, and rear panels provide you with easy cable routing.
Who will provide the computing infrastructure?
The project separates the roles of the facility owner, compute tenants and connectivity providers:
- Bell: developing the physical facility, providing connectivity and pursuing enterprise and public-sector commercialization.
- Cerebras: supplying wafer-scale systems intended for high-performance AI training and inference.
- CoreWeave: providing scalable AI cloud compute hosted on NVIDIA GPUs.
- SaskTel: partnering on connectivity and the marketing of AI-powered products and solutions to SaskTel customers.
- SaskPower: supplying the facility’s utility power and supporting its grid connection.
Bell says Cerebras and CoreWeave have signed long-term agreements covering the facility’s capacity. That gives the project two announced commercial anchors, but it also means the development’s initial tenant base is concentrated in two companies.
What “sovereign AI compute” means
Bell says a significant portion of the centre will be dedicated to “sovereign AI compute” for Canadian governments, researchers and enterprises. In practical terms, this is intended to give customers an option to run sensitive workloads while maintaining Canadian data residency and chain-of-custody requirements.
That claim should not be interpreted as proof that every part of the technology stack is Canadian-owned. The facility will rely on compute infrastructure from Cerebras and CoreWeave, and Bell describes CoreWeave’s systems as using NVIDIA GPUs. Canadian hosting can address where data is stored and processed, but it does not automatically resolve questions about foreign ownership, legal jurisdiction, software dependencies, cybersecurity or supply-chain exposure.
Bell has not publicly specified what percentage of the 300MW will be reserved for sovereign workloads. It also has not established that every Canadian customer will automatically be eligible to use the site.
How the project will be financed
Bell’s financial disclosures distinguish the facility investment from the tenant hardware:
Rank #3
- Adjustable Depth: 23-40'' adjustable depth is used for servers and network equipment, ensuring enough space for AV equipment, components, and cabling, while allowing you to access ports and equipment from multiple sides.
- Strong Load Capacity: Ground-Mounted Load Capacity: 500 lbs, Wall-Mounted Load Capacity: 150 lbs. The av rack is made of carbon steel for better weldability performance and can help save space while meeting your need to place multiple devices.
- User-friendly Design: Ergonomic design makes the open frame av rack easier to use. The additional top panel is able to place other items with more available space. Roller design moves anywhere and anytime, is convenient, and is more energy-saving.
- Complete Accessories: We provide the accessories you need, including 2 x Pallets, 145 x M5*10 Cross Head Screws, 4 x Casters, 4 x M10*50 Expansion Screws,10 x M6*12 Cage Nuts, 1 x Grounding Wire, 1 x User Manual.
- Wide Application: The server rack wall mount maximizes the use of available space, suitable for retail venues, classrooms, offices, and other places where space is limited.
| Item | What Bell has said |
|---|---|
| Physical facility | Approximately $1.7 billion in Bell capital expenditure |
| Expected 2026 spending | Approximately $1.3 billion |
| AI servers and compute hardware | To be supplied and funded separately by Cerebras and CoreWeave |
| Projected Saskatchewan economic value | Up to $12 billion over the long term |
Bell says the physical-facility investment will be funded through a combination of debt financing and cash on hand, according to its Q1 2026 shareholder report.
The frequently cited $12 billion figure is not Bell’s construction budget, a government payment or a guaranteed return. It is a projected measure of long-term economic value cited by Bell and the Saskatchewan government.
How Saskatchewan’s electricity supply fits in
Bell’s project materials say the facility will receive 300MW of utility power from Saskatchewan’s grid and will be located beside an existing SaskPower substation. Bell’s presentation describes the provincial electricity mix as including gas, hydro and coal.
The Tool Desk
Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →As a result, the project should not be described as renewable-powered based on the announcement materials alone. The documents do not fully explain:
- what grid upgrades will be required;
- who will pay for interconnection and related infrastructure;
- whether the full 300MW will be available immediately or in stages;
- how peak demand and backup generation will be managed;
- the facility’s expected annual electricity consumption; or
- its final emissions and water-use profile.
These are important issues for Saskatchewan households, businesses and investors to monitor. A large industrial load can raise questions about system capacity, reliability, cost allocation and competing demand, but the available announcements do not establish that the project will increase electricity rates or reduce reliability.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Jobs and projected economic benefits
Bell and Saskatchewan government estimates include:
Rank #4
- An intelligent fan system designed for cooling audio video, DJ, server, network, and IT equipment racks.
- Protects rack-mount equipment from overheating, performance issues, and shortened lifespans.
- Programmable thermostat controller with automated speed control, alarm warnings, and backup memory.
- Premium anodized aluminum construction with CNC-machined detailing for a professional appearance.
- Size: 1U Rack Space | Design: Top Exhaust | Airflow: 60 to 300 CFM | Noise: 12 to 38 dBA | Bearings: Dual Ball
- at least 800 construction, engineering and technical jobs supported across multiple phases;
- up to 80 full-time operating roles once the facility is running;
- as many as 750 additional community jobs, based on industry research; and
- up to $12 billion in long-term economic value for Saskatchewan.
The distinction between these numbers matters. The 800-job figure concerns construction and development activity, not permanent employment. The 750 community-job estimate is an indirect, industry-based projection rather than a committed hiring target. The $12 billion figure is also a projection, not guaranteed GDP growth, government revenue or Bell’s direct investment.
Quick wins for a faster PC:
Repair Windows errors before they cause bigger problemsFix Now →Scan for outdated or missing drivers - takes under a minuteDriver Scan →Construction status and timeline
The project has progressed beyond the initial announcement, but it was not operational as of August 16, 2026:
- March 16, 2026: Bell and Saskatchewan announced the planned 300MW AI data centre.
- April 20: The RM of Sherwood approved the development agreement.
- April 21: Early site work began.
- May 4: Bell announced contractors involved in early project phases.
- May 14: Bell announced additional construction partners and a long-term relationship with Bird Construction.
- First half of 2027: Bell says the first data halls are expected to come online.
Other named project participants include Bird Construction, the Architect of Record Alton Tangedal Architect Ltd., and George Gordon Developments for site services. Construction-partner announcements show mobilization and procurement progress; they do not prove that the full facility has been completed, energized or occupied.
What readers should still watch
The project is significant for Canadian AI infrastructure, but several commercial and public-interest details remain undisclosed. Future updates should clarify:
- the exact allocation of capacity to sovereign Canadian workloads;
- customer eligibility, pricing, contract sizes and service-level commitments;
- the cost and responsibility for grid upgrades;
- water consumption and cooling design;
- backup-power arrangements and emissions;
- the final construction cost; and
- whether the first-half-of-2027 target changes.
Bell, CoreWeave and Cerebras have not established a public, self-serve sign-up path or Saskatchewan-specific hourly GPU pricing in the cited materials. The project is therefore best understood as enterprise infrastructure, not a consumer cloud product that individuals can immediately purchase.
Recommended Free Tools
Sources: Bell announcement, Bell backgrounder, Bell project presentation, Government of Saskatchewan announcement, and Bell’s construction-partner update.
Quick Recap
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.